Jackson Township Advances Infrastructure Projects Despite Winter Conditions
Jackson Township continues progress on major infrastructure improvements while maintaining winter road operations, officials reported at the January 8 township meeting.
Supervisor Matt Robbins updated the board on the ongoing utility pole relocation project, saying design work is nearing completion. “The design is in progress and scheduled for completion this week and submitted to ComEd for approval,” Robbins said.
The township is also moving forward with engineering proposals from Ruettiger and Tonelli, who are “working on finalizing the engineering proposal and had a few questions that Supervisor Robbins was able to answer.”
Highway Commissioner Walsh reported that road crews have been conservative with salt application this winter due to limited snowfall. “There has not been a lot of snow so far this winter, but they did get out on Monday and did spread salt,” Walsh said. “They won’t spread salt until something actually falls just to ensure they are using resources effectively.”
Walsh also announced progress on equipment acquisition, meeting with a Rush Trucks salesman to sign a contract for a new township vehicle.
The infrastructure updates come as Jackson Township prepares for what could be a busy construction season once weather conditions improve. The utility work and engineering projects represent significant capital investments in the township’s long-term infrastructure needs.
Township officials emphasized their commitment to responsible resource management, both in winter road maintenance and capital project planning.
Community Events
Latest News Stories
Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings
Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025
Manhattan Park Board Hires New Architect for Round Barn Buildout, Secures Annexation for Future Banquet Hall
Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases
Manhattan School District 114 Approves $41.5 Million Budget for FY26
Manhattan Fire District Advances New Station with $8.75M Bond Hearing, Approves Contracts with $194,000 Savings
Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements
Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign
“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension
Will County Grants Extensions to Five Solar Projects Sold to New Developers
Will County Board Approves Controversial Drug Recovery Retreat in Crete Township