Road Contract Awarded as Township Races Against Bridge Funding Deadline
The Manhattan Township Highway Department has awarded a $91,000 contract for its annual road resurfacing program, while simultaneously facing a critical deadline that puts $500,000 in county funding for a major bridge project at risk.
At the April 8 township meeting, Highway Commissioner Jim Baltas announced that Steffens 3D Construction submitted the winning bid for this year’s tar and chip projects. The $91,000 price tag does not include the cost of stone, which the Road District will supply itself. To highlight rising costs, Commissioner Baltas noted that a similar project in 2016 cost only $36,000.
More urgently, the commissioner reported that the Kankakee Street Bridge replacement project is scheduled to go out for bids by July 16, 2025. If the bidding process is delayed beyond August 2025, the township will lose a $500,000 grant from Will County earmarked for the construction. The anticipated start date for the bridge work is spring 2026.
In other highway news, the demolition of the Baker Road Bridge began in early April as planned. The board approved the highway commissioner’s expenses as part of the finance report.
Latest News Stories
Committee: Facilities Department Reports $92,000 in Energy Savings, Completes Veterans Assistance Commission Buildout
Lemont Pulls Away from Lincoln-Way West in 10-3 Non-Conference Defeat
Nebraska voters to elect party representatives
U.S. farmers struggling with high price of fuel, fertilizer as bankruptcies rise
Trump, Xi meeting to be packed with slew of hot topics
Manhattan District 114 Reviews Major Board Policy Overhaul
Green Garden Solar Farm Approved in Split Vote; Battery Storage Component Rejected
Lockport Tops Lincoln-Way West in Tight Conference Battle
Lincoln-Way East Outlasts Lincoln-Way West in 10-6 Conference Victory
Bill to expel students over sexual assault progresses in Springfield
Viral goose egg case fuels debate over abortion
Another U.S.-Canada border bust: Gun smuggling operation