Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Screenshot 2025-12-05 at 11.56.48 AM

Tensions Flare as Board Members Clash Over Budget Process and Protocol

Will County Board Meeting | December 4, 2025 Article Summary: A special meeting intended to fix a budget error turned contentious as board members traded accusations regarding transparency, meeting conduct,...
Screenshot 2025-12-05 at 11.57.25 AM

Will County Board Approves $2.7 Million Reserve Draw to Finalize 0% Tax Levy

Will County Board Meeting | December 4, 2025 Article Summary: The Will County Board unanimously voted to transfer approximately $2.78 million from cash reserves to balance the fiscal year 2026...
Untitled design - 1

Manhattan-Elwood Library District Board Approves 2026-2030 Strategic Plan and Tax Levy

Manhattan-Elwood Public Library District Board Meeting | October 2025 Article Summary: The Manhattan-Elwood Public Library District Board of Trustees secured the institution's financial and operational future on Tuesday by approving...
Screenshot 2025-12-04 at 11.29.34 AM

Manhattan Annexes Historic Round Barn Farm; Plans for Wedding Venue Move Forward

Village of Manhattan Board of Trustees Meeting | December 2, 2025 Article Summary: The Manhattan Village Board officially annexed the historic Round Barn Farm Park into the village limits, paving...

Jackson Township to Hear Proposal for Manure-to-Gas Energy Facility

Article Summary: A proposal for an anaerobic digester facility that would convert hog manure into natural gas was brought to the attention of the Jackson Township Board. The project manager...

Meeting Summary and Briefs: Manhattan School District 114 for November 12, 2025

Manhattan School District 114 Meeting | November 12, 2025 The Manhattan School District 114 Board of Education held a meeting marked by profound community grief, a parent's emotional plea for...
Meeting-Briefs

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 for November 20, 2025

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 The Lincoln-Way Community High School District 210 Board of Education held a busy meeting on Thursday, November 20, 2025,...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Park Board for October 2025

Manhattan Park Board Meeting | October 9, 2025 The Manhattan Park Board on Thursday, October 9, 2025, unanimously rejected a proposal for a conceptual site plan after developers declined to...
WATCH: California starts portal for complaints about ICE

WATCH: California starts portal for complaints about ICE

By Dave MasonThe Center Square On Wednesday, California launched a website portal for residents who believe they’ve seen unlawful actions by federal agents, including U.S. Immigration and Customs Enforcement officers....
Trump signs drug treatment bill backed by Colorado representative

Trump signs drug treatment bill backed by Colorado representative

By Elyse ApelThe Center Square President Donald Trump just signed the SUPPORT for Patients and Communications Reauthorization Act, which was spearheaded by U.S. Rep. Brittany Pettersen, into law. The act...
Chicago aldermen advance ordinance to restrict hemp sales

Chicago aldermen advance ordinance to restrict hemp sales

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A Chicago city council committee has advanced an ordinance that would ban most hemp sales in the...
White House to roll back Biden fuel economy standards

White House to roll back Biden fuel economy standards

By Morgan SweeneyThe Center Square The federal government is relaxing Biden-era fuel economy standards that required most cars to have a fuel efficiency of nearly 50 mpg by 2031 in...
DEA says fentanyl purity dropping amid pressure campaign

DEA says fentanyl purity dropping amid pressure campaign

By Brett RowlandThe Center Square The U.S. Drug Enforcement Administration said fentanyl purity is declining amid a government-wide effort to address the threat of synthetic opioids. President Donald Trump has...
GAO confirms large-scale, systemic fraud risk in expanded Obamacare subsidies

GAO confirms large-scale, systemic fraud risk in expanded Obamacare subsidies

By Thérèse BoudreauxThe Center Square The enhanced Obamacare subsidies that Democrats want to extend are virtually unprotected against fraud, costing taxpayers potentially billions of dollars a year, a bombshell report...
San Francisco sues companies over 'ultra-processed' foods

San Francisco sues companies over ‘ultra-processed’ foods

By Dave MasonThe Center Square The city and county of San Francisco is suing 10 companies for manufacturing everything from sodas to candy bars and breakfast cereals - what the...