Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Screenshot 2025-11-21 at 1.05.56 PM

Manhattan Greenlights 41-Lot Butternut Ridge South, Advances Wastewater Plant Expansion

Manhattan Village Board Meeting | November 18, 2025 Article Summary:The Manhattan Village Board approved two major infrastructure projects, giving final plat approval for the 41-lot Butternut Ridge South subdivision and...
solar panels photovoltaics in solar farm

New Lenox to Host Large Pollinator-Friendly Solar Farm

Will County Board Meeting | November 2025 Article Summary: The Will County Board unanimously approved a special use permit for a commercial solar energy facility spanning approximately 63 acres in...
joliet junior college logo

JJC Receives Clean Audit, Reports $21.6 Million Increase in Net Position

Joliet Junior College Meeting | November 12, 2025 Article Summary:Joliet Junior College received a "clean unmodified audit opinion" for the fiscal year ending June 30, 2025, the highest level of...
Everyday Economics: Rear-view jobs strength, forward-looking weakness in week ahead

Everyday Economics: Rear-view jobs strength, forward-looking weakness in week ahead

By Orphe DivounguyThe Center Square The September jobs report was a look in the rear-view mirror in more ways than one. Because of the 43-day government shutdown, we didn’t get...
will county board graphic

Will County Board Passes 0% Tax Levy, Creating “Unbalanced” Budget Crisis

Will County Board Meeting | November 2025 Article Summary: In a contentious fiscal showdown, the Will County Board voted to keep the corporate property tax levy flat, rejecting a proposed...
Poll: Majority of Americans still support legal immigration

Poll: Majority of Americans still support legal immigration

By Andrew RiceThe Center Square A majority of Americans say that legal immigration is good for the United States, according to a new poll commissioned by The Center Square. The...
New Illinois youth center begins housing youth in Lincoln

New Illinois youth center begins housing youth in Lincoln

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) - After a short delay to finalize staffing and safety preparations, the new Monarch Center in Lincoln...
State officials urge Trump, Congress to address national debt

State officials urge Trump, Congress to address national debt

By Brett RowlandThe Center Square Indiana Gov. Mike Braun and a coalition of state financial officers and lawmakers are urging Congress and President Donald Trump to address the national debt...
Will County P&Z Logo Planning Zoning

Committee Advances Special Use Permit for Used Car Dealership in New Lenox Township

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission has approved a special use permit for a light equipment sales...
Bus 210

Lincoln-Way 210 to Purchase 31 Buses, Citing Major Savings Over Leasing

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: The Lincoln-Way District 210 Board of Education approved the purchase of 28 yellow school buses and three white...
War Department, VA have highest number of unresolved audit recommendations

War Department, VA have highest number of unresolved audit recommendations

By Morgan SweeneyThe Center Square Of the 15 federal executive departments that compose the president’s Cabinet, the Departments of War and Veterans Affairs have the most unresolved, open recommendations for...
Nearly 550 truck drivers cited for not understanding English in Illinois YTD

Nearly 550 truck drivers cited for not understanding English in Illinois YTD

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – The number of English language proficiency violations for commercial drivers in Illinois year-to-date has nearly eclipsed last...
Envelopes with white powder sent to two Texas ICE offices, no public threat

Envelopes with white powder sent to two Texas ICE offices, no public threat

By Bethany BlankleyThe Center Square Texas remains ground zero for targeted attacks against U.S. Immigration and Customs Enforcement officers. In the past few months, ICE facilities in Texas have been...
Georgia GOP thanks Greene; Trump says she 'went bad'

Georgia GOP thanks Greene; Trump says she ‘went bad’

By Kim JarrettThe Center Square Less than 24 hours after the surprise resignation of U.S. Rep. Marjorie Taylor Greene, the Georgia Republican received thanks from the state Republican Party and...
Texas governor, members of Congress lead effort to ban Sharia law in US

Texas governor, members of Congress lead effort to ban Sharia law in US

By Bethany BlankleyThe Center Square An anti-Sharia law movement is being led by Texas Republicans, including Texas’ governor and members of Congress. Gov. Greg Abbott this week issued three directives...