Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

WATCH: CA Democrats pass congressional redistricting plan

WATCH: CA Democrats pass congressional redistricting plan

By Dave MasonThe Center Square After a day of vigorous debates punctuated by occasional applause, both houses of the California Legislature Thursday passed the three bills making up the congressional...
Pew: U.S. immigrant population declines for first time in nearly 60 years

Pew: U.S. immigrant population declines for first time in nearly 60 years

By Caroline BodaThe Center Square The U.S.’s foreign-born population shrunk this year for the first time since the 1960s, new data released Thursday from the nonpartisan Pew Research Center found....
WATCH: Illinois’ FY23 financial audit released amid criticism of tardy reports

WATCH: Illinois’ FY23 financial audit released amid criticism of tardy reports

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Illinois taxpayers can now look at how the state spent their money in the fiscal year that...
European Union says U.S. consumers will end up paying tariffs

European Union says U.S. consumers will end up paying tariffs

By Brett RowlandThe Center Square European Union leaders detailed the terms of a trade deal they struck with President Donald Trump on Thursday, making sure to point out who will...
Illinois quick hits: Anti-SLAPP bill signed; Chicago schools settles meditation case

Illinois quick hits: Anti-SLAPP bill signed; Chicago schools settles meditation case

By Jim Talamonti | The Center SquareThe Center Square Anti-SLAPP bill signed Gov. J.B. Pritzker has signed legislation to protect news media from strategic lawsuits against public participation (SLAPP). The...
U.S.-EU trade deal includes ceiling for European pharmaceutical imports

U.S.-EU trade deal includes ceiling for European pharmaceutical imports

By Morgan SweeneyThe Center Square The European Union has escaped a potential 250% pharmaceutical tariff and instead has secured a maximum 15% levy with the U.S. according to a joint...
Supreme Court allows Trump to block DEI funding

Supreme Court allows Trump to block DEI funding

By Andrew RiceThe Center Square The U.S. Supreme Court, in a 5-4 decision on Thursday, allowed President Donald Trump to cut hundreds of millions of dollars in federal research grants....
Trump to probe Smithsonian museums for 'woke' ideology

Trump to probe Smithsonian museums for ‘woke’ ideology

By Andrew RiceThe Center Square President Donald Trump has promised to crack down on “woke” ideas promoted in museums across the United States, including the federally funded Smithsonian museums in...
Director: Nation’s largest outdoor ag show brings economic impact to central IL

Director: Nation’s largest outdoor ag show brings economic impact to central IL

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The nation’s largest outdoor agricultural show is set for next week in Central Illinois. The Farm Progress...
NY appeals court overturns Trump's civil fraud penalty

NY appeals court overturns Trump’s civil fraud penalty

By Chris WadeThe Center Square A New York appeals court has tossed out a $454 million civil fraud verdict against Donald Trump and his family business over charges he broke...
Planning & Zoning Graphic.3

Will County P&Z: Washington Township Lot Variance Granted

A variance to reduce the minimum lot area from 10 acres to 5 acres was unanimously approved for a property at 1444 E. Corning Road in Washington Township. The owner,...
solar panels photovoltaics in solar farm

Will County P&Z Approves Crete Solar Farm, Overruling Township’s General Opposition

Article Summary: The Will County Planning and Zoning Commission recommended approval for a new commercial solar farm in Crete Township, moving the project forward despite being informed by staff of...
P&Z 8.19.25

Will County Board Approves Controversial Recovery Retreat in Crete Township Amid Strong Resident Opposition

Article Summary: The Will County Planning and Zoning Commission approved a special use permit for a long-term residential recovery program on a 68-acre horse farm, despite vocal opposition from Crete...

Will County P&Z: Green Garden Township Variances Granted in Monee

Roy F. Erikson received unanimous approval for two variances for his property at 26409 S. 80th Avenue in Monee. The Will County Planning and Zonning Commission approved reducing the minimum...

Will County P&Z: Manhattan Township Rezoning Approved

The Will County Planning and Zonning Commission unanimously approved a map amendment for a vacant property on South Kankakee Street in Manhattan Township. The request, brought by James and Julie...