Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for August 5, 2025

The future of several key county facilities dominated the Will County Capital Improvements & IT Committee meeting on Tuesday. A major topic of discussion was the ongoing buildout of the...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for August 7, 2025

The Will County Board Public Health & Safety Committee on Thursday heard urgent requests for facility and funding support from two of the county’s key public-facing departments. The committee took...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for August 7, 2025

The Will County Board Public Health & Safety Committee on Thursday heard urgent requests for facility and funding support from two of the county’s key public-facing departments. The committee took...
Meeting Briefs

Meeting Summary and Briefs: Will County Land Use & Development Committee for August 7, 2025

The Will County Land Use & Development Committee tackled two contentious zoning cases during its August 7 meeting, denying a special use permit for a landscaping business in a residential...

Meeting Summary and Briefs: Will County Planning and Zoning Commission for August 5, 2025

The Will County Planning and Zoning Commission backed two controversial projects at its August 5 meeting, unanimously approving a large-scale landscaping business on a residential lot in DuPage Township despite...
Meeting Briefs

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for August 5, 2025

The Will County Public Works & Transportation Committee received a detailed presentation on "Our Way Forward 2050," a new 25-year long-range plan designed to guide the region's transportation infrastructure through...
Texas House sues six Democrats absconding in California

Texas House sues six Democrats absconding in California

By Bethany BlankleyThe Center Square Following through on his pledge to use all means necessary to find, arrest and return absconding House Democrats to Texas, the Texas House, led by...
With antisemitism on the rise, a glimmer of hope at Jewish delis

With antisemitism on the rise, a glimmer of hope at Jewish delis

By Bethany BlankleyThe Center Square With antisemitism at its highest level in recorded history, Jewish delis in the U.S. are providing a glimpse of hope, celebration and award-winning pastrami on...
‘Exactly what we need’: First expedited coal lease advances

‘Exactly what we need’: First expedited coal lease advances

By Tate MillerThe Center Square The first expedited coal lease under the Big Beautiful Bill has advanced with the goal of energy independence and job creation in mind. An energy...
In six months, ICE arrests 350 gang members in Houston

In six months, ICE arrests 350 gang members in Houston

By Bethany BlankleyThe Center Square In the first six months of the Trump administration, U.S. Immigration and Customs Enforcement officers in Houston arrested 356 illegal foreign nationals who are confirmed...
Multiple briefs filed with Texas Supreme Court in Abbott lawsuit against Wu

Multiple briefs filed with Texas Supreme Court in Abbott lawsuit against Wu

By Bethany BlankleyThe Center Square Multiple individuals have filed amicus briefs with the Texas Supreme Court in response to an emergency writ of quo warranto petition filed by Texas Gov....
Pasco Mayor Pete Serrano to take Trump appointment as Eastern WA U.S. attorney

Pasco Mayor Pete Serrano to take Trump appointment as Eastern WA U.S. attorney

By Carleen JohnsonThe Center Square President Donald Trump has nominated Pete Serrano – mayor of Pasco, Wash. – to be the next U.S. Attorney for the Eastern District of Washington....
President Trump hosts Armenia, Azerbaijan for peace treaty signing

President Trump hosts Armenia, Azerbaijan for peace treaty signing

By Morgan SweeneyThe Center Square President Donald Trump hosted the leaders of Armenia and Azerbaijan at the White House Friday to sign what is reportedly the first peace deal both...
Trump, Putin to meet next week

Trump, Putin to meet next week

By Sarah Roderick-FitchThe Center Square More than three years after Russia invaded Ukraine, progress in achieving peace in the region could be on the horizon as President Donald Trump has...
Bill would codify Trump's executive order banning 'woke' debanking

Bill would codify Trump’s executive order banning ‘woke’ debanking

By Thérèse BoudreauxThe Center Square In light of President Donald Trump signing an executive order that effectively bans politically-driven debanking, a Kentucky lawmaker plans to introduce legislation codifying fair access...