Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Will County Board Graphic.02

Committee Advances Nearly $212,000 in Road and Facility Contracts for Jackson Township and Monee

Will County Board Public Works & Transportation Committee Meeting | May 5, 2026 Article SummaryThe Will County Public Works and Transportation Committee approved two infrastructure contracts totaling over $212,000 for...
Will County Board Graphic.03

Will County Committee Hits Brakes on License Plate Reader Agreements Awaiting Privacy Policy Review

Will County Board Public Works & Transportation Committee Meeting | May 5, 2026 Article SummaryThe Will County Public Works and Transportation Committee delayed votes on five intergovernmental agreements for Automated...
Will County Board Graphic.03

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for May 5, 2026

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026 The Will County Board Capital Improvements & IT Committee focused heavily on long-term infrastructure planning during its...
Pittsburgh nurses lead charge for paid leave, for everyone

Pittsburgh nurses lead charge for paid leave, for everyone

By Christen SmithThe Center Square Nurses across southwestern Pennsylvania see a simple answer to record-breaking staffing shortages and worsening healthcare outcomes for mothers and babies: paid family leave, not just...
Existing-home sales edge up in April as affordability improves

Existing-home sales edge up in April as affordability improves

By Brett RowlandThe Center Square Existing-home sales rose 0.2% in April to a seasonally adjusted annual rate of 4.02 million, rebounding after a 3.6% drop in March, according to the...
Accused correspondents' dinner shooter pleads not guilty to all charges

Accused correspondents’ dinner shooter pleads not guilty to all charges

By Andrew RiceThe Center Square The accused White House Correspondents' Association Dinner shooter pleaded not guilty in federal court on Monday to all charges, including an attempt to assassinate President...
Illinois Quick Hits: Diesel passes $6; unleaded price drops

Illinois Quick Hits: Diesel passes $6; unleaded price drops

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The average price for a gallon of diesel fuel in Illinois has gone over the $6 mark...
U.S. Senate panel to examine fertilizer costs, food prices

U.S. Senate panel to examine fertilizer costs, food prices

By Tom JoyceThe Center Square The U.S. Senate Agriculture Committee will hold a hearing on Tuesday afternoon looking at disruptions in the fertilizer industry and the impact rising costs are...
Will County P&Z Logo Planning Zoning

Green Garden Solar Project Cleared to Implement Higher “Agrivoltaic” Standards

Will County Planning and Zoning Commission Meeting | May 5, 2026 Article Summary: The Will County Planning and Zoning Commission approved four variances on Tuesday, May 5, 2026, to facilitate...

Everyday Economics: Stable but weak under the surface

By Orphe DivounguyThe Center Square The April jobs report looked fine. Payrolls rose, unemployment held at 4.3%, hours ticked up. Nothing broke. But look one layer down and the picture...
Will County Board Graphic.01

Committee: Facilities Department Reports $92,000 in Energy Savings, Completes Veterans Assistance Commission Buildout

Will County Board Capital Improvements & IT Committee Meeting | May 5, 2026 Article SummaryAssistant Director of Facilities Ken Rogalski reported significant energy savings and the completion of key county...
Lincoln Way West Warriors Baseball

Lemont Pulls Away from Lincoln-Way West in 10-3 Non-Conference Defeat

The Lincoln-Way West varsity baseball team traveled to Lemont on Saturday for a non-conference matchup, ultimately dropping the contest 10-3 despite a mid-game offensive rally. Lemont jumped out to an...
Nebraska voters to elect party representatives

Nebraska voters to elect party representatives

By Andrew RiceThe Center Square Voters in Nebraska will head to the polls on Tuesday to nominate party representatives for U.S. Senate, U.S. House and the state legislature. Prominent incumbents...
U.S. farmers struggling with high price of fuel, fertilizer as bankruptcies rise

U.S. farmers struggling with high price of fuel, fertilizer as bankruptcies rise

By Thérèse BoudreauxThe Center Square As Congress continues working on the long-overdue federal farm bill, American farmers entering planting season are facing a grim financial landscape. Due to the U.S.-Iran...
Trump, Xi meeting to be packed with slew of hot topics

Trump, Xi meeting to be packed with slew of hot topics

By Sarah Roderick-FitchThe Center Square After postponing a scheduled trip to China from March to May due to the U.S. strikes on Iran, President Donald Trump is set to visit...