Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Civil rights complaints filed over race-based healthcare scholarships

Civil rights complaints filed over race-based healthcare scholarships

By Elyse ApelThe Center Square A nonprofit advocacy group has filed federal civil rights complaints against two healthcare systems, alleging their scholarship programs unlawfully exclude applicants based on race. Do...
Candidates clamor for Carter's open seat

Candidates clamor for Carter’s open seat

By Andrew RiceThe Center Square U.S. Rep. Buddy Carter's decision to run for U.S. Senate has attracted 14 candidates for his 1st Congressional District post. Carter, a Republican, has served...
Illinois Quick Hits: Civic federation funds 'persistent structural imbalance' in Illinois

Illinois Quick Hits: Civic federation funds ‘persistent structural imbalance’ in Illinois

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A new Civic Federation report has identified a persistent structural imbalance in the Illinois budget, with expenditures...
Screenshot 2026-04-25 at 8.34.35 AM

Lincoln-Way Schools Join “WillBeReady” Mutual Aid Network for Disaster Response

Lincoln-Way Community High School District 210 Meeting | April 16, 2026 Article Summary: The Lincoln-Way Board of Education approved a Memorandum of Understanding to join the "WillBeReady" Mutual Aid Network,...
Will County Board Graphic.01

Millions Approved for Will County Highway and Road Infrastructure Projects

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board authorized nearly $4.3 million in road improvement contracts, targeting key corridors including Francis Road, Renwick Road,...
U.S. House OKs Fetterman bill allowing SNAP to cover hot rotisserie chicken

U.S. House OKs Fetterman bill allowing SNAP to cover hot rotisserie chicken

By John ColeThe Center Square A bill that would allow recipients of the Supplemental Nutrition Assistance Program, or SNAP, to buy hot rotisserie chicken is one step closer to becoming...
Gas hits $6 a gallon in California; Southwest see increases

Gas hits $6 a gallon in California; Southwest see increases

By Liam HibbertThe Center Square California Thursday officially exceeded an average gas price of $6 a gallon for the first time since the start of the U.S.-Israel conflict with Iran....
Teacher unions spent over $1B on political causes since 2015

Teacher unions spent over $1B on political causes since 2015

By Esther WickhamThe Center Square National teachers unions have spent over $1 billion on political activity and advocacy since 2015, according to a new report by Defending Education. Both reports,...
Illinoisans may soon need registration, title, license to use e-bikes, scooters

Illinoisans may soon need registration, title, license to use e-bikes, scooters

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Illinoisans may soon be required to register their e-bikes, motorized scooters and other various modes of transport...
Executive order creates website for retirement accounts, matching federal contributions

Executive order creates website for retirement accounts, matching federal contributions

By Morgan SweeneyThe Center Square President Donald Trump signed an executive order Thursday aiming to expand access to “high-quality” retirement accounts to all Americans. The administration will launch a website...
Congress extends govt. surveillance powers for 45 days

Congress extends govt. surveillance powers for 45 days

By Thérèse BoudreauxThe Center Square The U.S. House has adopted a short-term extension of FISA Section 702, buying lawmakers more time to hammer out reforms to the controversial federal surveillance...
Report: 10% credit card cap could cut off 64 million Americans, risk recession

Report: 10% credit card cap could cut off 64 million Americans, risk recession

By Tom JoyceThe Center Square A proposed federal cap on credit card interest rates could drastically reduce Americans' access to credit and hurt the U.S. economy, a new report warns....
Pritzker’s commission report pushes for local investigations of federal 'brutality'

Pritzker’s commission report pushes for local investigations of federal ‘brutality’

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker’s Illinois Accountability Commission has released its report on alleged abuses by federal immigration law...

WATCH: Trump ‘probably’ considering pulling U.S. troops out of Italy, Spain

By Andrew RiceThe Center Square President Donald Trump on Thursday said he is considering removing U.S. military troops from Italy and Spain, due to the country's lack of assistance during...
Illinois mulls change allowing pension investment in anti-Israel companies

Illinois mulls change allowing pension investment in anti-Israel companies

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Multiple speakers shared personal stories Thursday from the conflict between Israeli forces and Palestinians in an effort...