Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

New park fee for foreign tourists could generate hundreds of millions

New park fee for foreign tourists could generate hundreds of millions

By Thérèse BoudreauxThe Center Square The Trump administration announced it is raising prices for nonresidents visiting national parks, a move that worries some tourism advocates but could generate hundreds of...
CDL proposals focus on safety as American truckers lose jobs, wages

CDL proposals focus on safety as American truckers lose jobs, wages

By Alan WootenThe Center Square Rising scrutiny of 194,000 state-issued nondomiciled CDLs to foreign workers with poor English language proficiency reveal two routes to safety. Rule change is one, done...
Trump's proposed $2,000 tariff rebates face costly challenges

Trump’s proposed $2,000 tariff rebates face costly challenges

By Brett RowlandThe Center Square President Donald Trump's plan to send some Americans $2,000 checks from the federal government's tariff collections is expected to cost more than the import duties...
Trump's legal fees could fall on the backs of Fulton County taxpayers

Trump’s legal fees could fall on the backs of Fulton County taxpayers

By Kim JarrettThe Center Square A law signed by Georgia Gov. Brian Kemp in May could put legal fees in the Donald Trump election interference case on the backs of...
Revenues from energy production at $14.6B for 2025

Revenues from energy production at $14.6B for 2025

By Alton WallaceThe Center Square Energy production on federal lands and waters and in U.S. tribal areas generated $14.61 billion in government revenues in the 2025 fiscal year, according to...
IL congressman’s retirement announcement sparks calls for election fixes

IL congressman’s retirement announcement sparks calls for election fixes

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Common Cause Illinois is urging lawmakers to close what it calls an “anti-democratic” loophole after Rep....
WATCH: Trump calls Pritzker ‘fat slob;’ Talk of reviving progressive tax criticized

WATCH: Trump calls Pritzker ‘fat slob;’ Talk of reviving progressive tax criticized

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop shares highlights from...
Illinois quick hits: Man arrested for threating legislator; vigilance urged during shopping season

Illinois quick hits: Man arrested for threating legislator; vigilance urged during shopping season

By Jim Talamonti | The Center SquareThe Center Square Man arrested for threating legislator Illinois State Police Division of Criminal Investigation special agents have arrested a Chicago man on charges...
Will County Board Graphic.01

County Takes Over “Central Will” Dial-A-Ride in Major Consolidation

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved an intergovernmental agreement to absorb the "Central Will" Dial-A-Ride system into the county-wide "Access Will County"...
Screenshot 2025-11-21 at 1.05.10 PM

Manhattan Officials Praise IDOT’s ‘Swift Action’ on Route 52, Discuss Further Safety Measures

Manhattan Village Board Meeting | November 18, 2025 Article Summary:Manhattan Mayor Mike Adrieansen thanked the Illinois Department of Transportation for its quick response in adding safety measures at the Route...
manhattan park district graphic.1

Manhattan Park Board Rejects Site Plan Proposal, Halts Planning Over Cost Dispute

Manhattan Park Board Meeting | October 9, 2025 Article Summary: The Manhattan Park Board unanimously rejected a proposal for an architectural concept site plan from Arete Design Studio, effectively pausing...
Will County Board Graphic.02

Board Denies Appeal for “Tiny Home” RV Living in Crete

Will County Board Meeting | November 2025 Article Summary: The Will County Board voted 19-2 to uphold a denial of a temporary use permit for a recreational vehicle (RV) being...
Jackson Township Graphic.1 NEW

Jackson Township Board Notified of Proposal for 800-Acre Data Center

Jackson Township Board Meeting | October 2025 Article Summary: During the monthly report, township officials announced the receipt of a public notice regarding a massive proposal to construct a data center...
joliet junior college logo

JJC Board Censures Trustee Broderick Twice, Denies Request to Restore Good Standing

Joliet Junior College Meeting | November 12, 2025 Article Summary:In a series of contentious votes, the Joliet Junior College Board of Trustees censured Trustee Maureen Broderick for two separate alleged...
mental health awareness day bipolar disorder anxiety stress emot

Will County Board Compromises on Mental Health Levy, Approves $10 Million After Debate

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board on Thursday, October 16, 2025, approved a $10 million tax levy for the Community Mental Health...