Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

White House calls for DHS funding after correspondents incident

White House calls for DHS funding after correspondents incident

By Andrew RiceThe Center Square The White House on Monday called on Congress to fund the U.S. Department of Homeland Security after shots were fired at the White House Correspondents'...
Report: $186 billion in federal payment errors likely an undercount

Report: $186 billion in federal payment errors likely an undercount

By Brett RowlandThe Center Square Federal agencies made an estimated $186 billion in improper payments in fiscal year 2025, a $24 billion increase from the prior year, according to a...
Convenience store advocate: Swipe fee ruling is 'one step' in the process

Convenience store advocate: Swipe fee ruling is ‘one step’ in the process

By Jim TalamontiThe Center Square *The Center Square) – The federal government has moved to partially block an Illinois law banning electronic processing fees on the tax and tip portions...
Report: Sharp ideological divide in Minnesota congressional delegation

Report: Sharp ideological divide in Minnesota congressional delegation

By Elyse ApelThe Center Square A new report analyzing congressional voting records shows a clear ideological divide between Minnesota’s Republican and Democratic delegations. In its idealogical rankings, the Institute for...
White House correspondents' dinner shooter faces formal charges

White House correspondents’ dinner shooter faces formal charges

By Thérèse BoudreauxThe Center Square The California man accused of charging security and shooting a Secret Service officer at the White House Correspondents' Association dinner Saturday night will appear Monday...
Deferred maintenance blamed in I-64 bridge hole

Deferred maintenance blamed in I-64 bridge hole

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – State transportation officials say repairs are underway after a large hole developed on an Interstate 64...
Supreme Court strikes down Texas redistricting lawsuit, upholds new maps

Supreme Court strikes down Texas redistricting lawsuit, upholds new maps

By Andrew RiceThe Center Square The U.S. Supreme Court on Monday struck down a challenge to Texas' new congressional maps. The court reversed Abbott v. LULAC, a case that sought...
Supreme Court to hear migrant farm worker case

Supreme Court to hear migrant farm worker case

By Andrew RiceThe Center Square The U.S. Supreme Court will hear a case over the constitutional authority of federal agencies to handle migrant farmworker disputes. The case, Department of Labor...
Illinois quick hits: Convicted felon suspected of shooting two officers; Chicago Mayor orders up to $900,000 for additional peacekeepers; Belleville man faces attempted murder charge

Illinois quick hits: Convicted felon suspected of shooting two officers; Chicago Mayor orders up to $900,000 for additional peacekeepers; Belleville man faces attempted murder charge

By Jim Talamonti | The Center SquareThe Center Square Convicted felony suspected of shooting two officers One Chicago police officer is dead and another was critically injured after a man...
Screenshot 2026-04-25 at 8.34.35 AM

Lincoln-Way D210 Approves $483,000 Agreement with Illinois Bone and Joint Institute, Adds Seventh Athletic Trainer

Lincoln-Way Community High School District 210 Meeting | April 16, 2026 Article Summary: The Board of Education approved a new three-year, $483,000 contract with the Illinois Bone and Joint Institute...
Peotone fire district graphic logo.1

Manhattan Fire Board Reviews Financials, Navigates ‘No Tax on Overtime’ Law

Manhattan Fire Protection District Meeting | March 16, 2026 Article Summary: The Manhattan Fire Protection District reviewed its early 2026 financial status while command staff outlined upcoming administrative hurdles, including compliance...
Lincoln Way West Warriors Baseball

Pitching Duo Dominates as Lincoln-Way West Baseball Edges Oak Forest 4-2

Relying on a stifling pitching performance and timely late-game execution, the Lincoln-Way West varsity baseball team secured a gritty 4-2 non-conference road victory over Oak Forest on Saturday afternoon. After...
Will County Board Graphic.02

Will County Passes Comprehensive Adult Entertainment Ordinance

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board passed Ordinance 26-133, enacting Chapter 119 of the Business Regulations to establish rigorous licensing, operational, and...
Screenshot 2026-04-25 at 9.20.57 AM

Manhattan Village Board Unanimously Adopts $32.7 Million Budget for Fiscal Year 2027

Village of Manhattan Meeting | April 21, 2026 Article Summary: The Manhattan Village Board gave final approval to a $32.7 million budget for the 2027 fiscal year, featuring substantial investments in...
Correspondents' dinner attacker detained with multiple weapons

Correspondents’ dinner attacker detained with multiple weapons

By Jon StyfThe Center Square A California man charged security with multiple weapons at a magnetometer screening area outside the White House Correspondents’ Dinner on Saturday night before he shot...