Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Screenshot 2026-02-22 at 4.29.56 PM

Advisory Committee Debates Rigor of Online Summer School Options

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The District 210 Advisory Committee reported on discussions regarding the potential expansion of online summer school offerings,...
Election Vote Graphic

Group Presents Allegations of 2024 Voter Roll Errors to County Board

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a resolution calling for the review of election systems and integrity, following public comments alleging inaccuracies...
manhattan fire district graphic logo.1

Manhattan Fire District Hires Three Full-Time Paramedics, Reports Progress on New Station

Manhattan Fire Protection District Meeting | Jan. 19, 2026 Article Summary: The Manhattan Fire Protection District Board authorized the immediate hiring of three firefighter/paramedics and prepared for a potential vacancy...
Will County Board Graphic.04

Will County Board Advised on Strict “Judicial” Role Ahead of Landfill Expansion Application

Will County Landfill Committee Meeting | February 10, 2026 Article Summary: During a detailed legal briefing on Tuesday, the Will County Landfill Committee received strict instructions regarding their conduct during...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Bath House Regulations Updated; Removes 60-Day Licensing Window

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee approved updates to the regulations governing bath houses and...
Committee-Land Use.Graphic

Land Use Committee Rejects Shorewood Solar Farm Despite 25-Year Lease Offer

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: The Will County Land Use and Development Committee voted against recommending a controversial solar farm proposal...
Screenshot 2026-02-22 at 5.06.42 PM

Trustees Renew Federal Lobbyist Contract Following $800,000 Funding Win

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The JJC Board voted to renew its contract for federal lobbyist services on Wednesday. Administration and supporting...
Committee-Executive.Graphic

Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road

Will County Executive Committee Meeting | February 11, 2026 Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in...
manhattan elwood library graphic.4

Meeting Summary and Briefs: Manhattan-Elwood Public Library District for January 26, 2026

Manhattan-Elwood Public Library District Meeting | January 26, 2026 The Manhattan-Elwood Public Library District Board of Trustees held a highly productive, 52-minute regular meeting on Monday afternoon to authorize capital...
Committee-Land Use.Graphic

Land Use Committee: ‘Clean Fill’ Proposal Stalls After Unauthorized Tree Removal Sparks Environmental Concerns

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: A request to rezone land for a "clean fill" operation in Joliet Township stalled in committee...
Screenshot 2026-03-22 at 12.12.19 PM

Manhattan School District Approves Tax Abatement and Fund Transfers

Manhattan School District 114 Meeting | February 11, 2026 Article Summary: The Manhattan School District 114 Board of Education unanimously approved two key financial resolutions to transfer operational funds and...
Screenshot 2026-02-22 at 4.29.56 PM

Contracts Approved for New West Principal and District Technology Director

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Board appointed Dr. Jennifer Killeen as the new Principal of Lincoln-Way West High School and Kyle...
manhattan elwood library graphic.2

Manhattan-Elwood Library Officially Adopts “Library of Things” Policies and Patron Waivers

Manhattan-Elwood Public Library District Meeting | January 26, 2026 Article Summary: Patrons will soon have new non-traditional borrowing options after the library board formally adopted policies and liability waivers to govern...
Committee-Planning & Zoning.Graphic

Meeting Summary and Briefs: Will County Planning and Zoning Commission for February 17, 2026

Will County Planning and Zoning Commission Meeting | February 17, 2026 JOLIET, IL – The Will County Planning and Zoning Commission met on Tuesday, February 17, 2026, with Acting Chairman John...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Liquor Ordinance Stalls Over Drafting Errors; Debates License Cap Policy

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee postponed a vote on the comprehensive update to the...