Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Illinois business group warns of 'backbreaking' progressive income tax

Illinois business group warns of ‘backbreaking’ progressive income tax

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Manufacturers say legislators at the Illinois State Capitol have done enough damage and a progressive tax would...
Illinois tops U.S. in pumpkin production despite recent decline in value

Illinois tops U.S. in pumpkin production despite recent decline in value

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Despite a recent decline in production value, Illinois is far and away the leader when it comes...
Congress moves to restore federal union powers, critics warn of higher costs

Congress moves to restore federal union powers, critics warn of higher costs

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – The U.S. Congress is set to vote on House Resolution 2550, a bill that would restore...
Ukraine agrees to preliminary peace plan; Russian strikes continue

Ukraine agrees to preliminary peace plan; Russian strikes continue

By Sarah Roderick-FitchThe Center Square Ukraine has agreed to a peace deal in hopes of ending the over three-year war with Russia, according to the White House. Following talks in...
Illinois quick hits: Chiropractor sentenced for fraud; fatal airport shooting investigation

Illinois quick hits: Chiropractor sentenced for fraud; fatal airport shooting investigation

By Jim Talamonti | The Center SquareThe Center Square Chiropractor sentenced for fraud A Chicago chiropractor has been sentenced to nearly six years in federal prison for billing a private...
Trump administration ends protected status for Burmese nationals

Trump administration ends protected status for Burmese nationals

By Tom JoyceThe Center Square The Trump administration is ending Temporary Protected Status for Burmese nationals, citing improved governance in the country and planned elections next month. The administration said...
Screenshot 2025-11-21 at 10.19.55 AM

Lincoln-Way 210 Receives Clean Audit, Financial Profile Score Downgraded to ‘Review’

Lincoln-Way Community High School District 210 Meeting | November 20, 2025 Article Summary: Lincoln-Way District 210 received a clean, unmodified opinion for its Fiscal Year 2025 audit, the highest rating possible....
Will County P&Z Logo Planning Zoning.2

Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial...
Trump designates Muslim Brotherhood as foreign terrorist organization

Trump designates Muslim Brotherhood as foreign terrorist organization

By Bethany BlankleyThe Center Square President Donald Trump on Monday issued an executive order to begin the process to designate the Muslim Brotherhood a foreign terrorist organization (FTO). Trump did...
Will County Logo Graphic

Speed Limits Lowered in Green Garden and Frankfort Neighborhoods

Will County Board Meeting | November 2025 Article Summary: The Will County Board adopted ordinances to establish new, lower speed limits in specific areas of Green Garden and Frankfort Townships....
Will County Board Graphic.02

Engineering Firm Hired for Gougar Road Bridge Replacement

Will County Board Meeting | November 2025 Article Summary: The Will County Board authorized a $301,000 contract for the design of a new bridge carrying Gougar Road over the Canadian...
Will County Board Graphic.03

Unpermitted Log Cabin and Stage Prompt Rezoning in Beecher

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved a zoning map amendment and variances for a property in Beecher to bring existing unpermitted structures...
OpenAI launches teachers AI tools for classrooms

OpenAI launches teachers AI tools for classrooms

By Esther WickhamThe Center Square OpenAI has introduced a new free version of ChatGPT for teachers, as artificial intelligence continues to grow within education. The new platform offers educators a...
Federal court blocks Trump from dismantling four agencies

Federal court blocks Trump from dismantling four agencies

By Dave MasonThe Center Square A federal court has issued a permanent injunction stopping the Trump administration from dismantling four federal agencies that deal with issues varying from libraries to...
State reps: Pritzker turns 'blind eye' to Chicago’s public safety crisis

State reps: Pritzker turns ‘blind eye’ to Chicago’s public safety crisis

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – After Gov. J.B. Pritzker said President Donald Trump was amplifying crime in Chicago, Illinois House Republicans said...