Manhattan Fire District Re-evaluating New Station Plans After Bids Come in Over Budget

Spread the love

Article Summary:

Construction bids for a new Manhattan Fire Protection District station have come in over the district’s maximum price, forcing officials to re-evaluate the project’s scope. Chief Steve Malone informed the Board of Trustees that the district is now working with its construction manager to identify cost-saving measures, a process that may require a special board meeting.

New Fire Station Project Key Points:

  • All submitted bids for the new fire station exceeded the district’s budget.

  • Chief Steve Malone said areas under review for cost reduction include roofing, insulation, HVAC, garage doors, and flooring.

  • A miscommunication regarding landscaping and property seeding is also being addressed.

  • The district is working with its construction manager, ICI Builds, to amend the project and control costs.

The Manhattan Fire Protection District is back to the drawing board on its new fire station project after construction bids came in higher than anticipated.

During the district’s board meeting on June 16, Fire Chief Steve Malone reported that the submitted bids all exceeded the project’s maximum budget. As a result, the district is now working with its construction manager, ICI Builds, to re-evaluate several components of the station’s design to bring costs back in line.

“New station bids have been received and came in over the max price, now we are looking to reevaluate a few things,” Malone told the board.

Among the areas being reviewed for potential savings are the station’s roofing, insulation, HVAC systems, garage doors, and flooring. Malone also noted there was a “miscommunication regarding seeding of the property” in the landscape bid that needs to be clarified. An addendum to the contract with ICI Builds will be required to reflect any changes.

Malone expressed hope that the review process would move quickly but acknowledged that the complexity of the issue might necessitate a special board meeting to approve a revised plan. The goal is to move forward without compromising the essential functions of the new facility.

In other business, Malone updated the board that the district is still awaiting the delivery of benches for the memorial site at Fire Station 83.

The Board of Trustees, including newly sworn-in member Mike Shivers, took the chief’s report under advisement. The district’s finances are otherwise in good shape, with accountant James Howard reporting that the budget is on track, interest rates on deposits are good, and real estate tax revenue is coming in as expected.

Latest News Stories

New-Lenox-Village-Board

Village Board Approves Millions in Spending on Roads, Parks, and Museum

NEW LENOX – The New Lenox Village Board authorized millions of dollars in spending on Monday for its annual road program and for continued investment in its newest community amenities,...
Meeting Briefs

Meeting Summary: New Lenox School District 122 Board of Education for June 17, 2025

The New Lenox School District 122 Board of Education handled significant financial business at its June 17 meeting, approving a tentative budget for the 2025-2026 school year and renewing insurance...
Meeting Briefs

Meeting Summary: New Lenox Board of Trustees for July 28, 2025

The New Lenox Village Board meeting on Monday was marked by ceremony and significant action on major developments. The board honored the new Pope Leo XIV and retiring Police Chief...
Meeting Briefs

Meeting Summary and Briefs: Monee Village Board for July 23, 2025

The Monee Village Board of Trustees heard a detailed presentation for a major industrial redevelopment, approved a significant payment for its nearly-completed public works facility, and gave final clearance for...
Fire-Accident-Emergency-Graphic.3

Fatal Crash, Second Collision Snarl Wilmington-Peotone Road

A fatal crash on Wilmington-Peotone Road Tuesday morning was complicated by a second, separate collision in the same area, prompting an extended closure of the roadway as emergency crews work...
new-lenox-fire-district-stations.2

New Lenox Fire Board Denies Variance Over Extreme Hydrant Distance, Citing Safety

NEW LENOX – The New Lenox Fire Protection District Board of Trustees unanimously denied a homeowner's variance request on Monday, citing significant public safety concerns over the property's extreme distance...
new-lenox-fire-district-stations.4

New Lenox Fire District Secures $35,000 Grant for UTV in Solar Farm Agreement

NEW LENOX – The New Lenox Fire Protection District is set to receive a $35,000 grant to purchase a new Utility Task Vehicle (UTV) as part of a community benefit...
Meeting Briefs

Meeting Summary: New Lenox Fire Protection District for June 16, 2025

The New Lenox Fire Protection District Board of Trustees took decisive action on a residential fire code variance and discussed a new community partnership for a planned solar farm during...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Township for June 2025

Manhattan Township Meeting | June 2025 The Manhattan Township Board passed its two largest annual fiscal items on Tuesday, June 10, 2025, unanimously approving township and road district budgets that...
Manhattan Township

Kankakee Street Bridge Project to Go to Bid in July; Baker Road Bridge 45% Complete

Manhattan Township Meeting | June 2025 Article Summary: Manhattan Township’s infrastructure program is moving forward on multiple fronts, with the Baker Road Bridge reconstruction now 45% complete and the larger Kankakee...
Ad-Hock-July-22nd

Will County Committee Forwards Overhauled Purchasing Code Amid Debate on Local Contractor Preference

The Will County Ad-Hoc Ordinance Review Committee advanced a major overhaul of the county's purchasing code Tuesday, but only after a split vote and a pointed debate over a separate,...
Ad-Hock-July-22nd

Finance Officials Clarify How Will County Tracks Assets, From Vehicles to Desks

Will County finance officials on Tuesday detailed the policies governing how the county tracks its physical and digital assets, explaining the $5,000 threshold for items that are formally capitalized and...
Ad-Hock-July-22nd

Will County Treasurer Confirms Free Online Tax Payment Option, Warns Against High Credit Card Fees

Will County Treasurer Tim Brophy confirmed Tuesday that property owners have a free online payment option available and advised residents to avoid the high convenience fees associated with using credit...
Ad-Hock-July-22nd

Committee Highlights ‘Lack of Teeth’ in County Code Enforcement Process

While the Will County Ad-Hoc Ordinance Review Committee quickly approved minor updates to its administrative adjudication ordinance Tuesday, the action sparked a broader discussion about resident frustration over the enforcement...
Meeting Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...