Kankakee Street Bridge Project to Go to Bid in July; Baker Road Bridge 45% Complete
Manhattan Township Meeting | June 2025
Article Summary: Manhattan Township’s infrastructure program is moving forward on multiple fronts, with the Baker Road Bridge reconstruction now 45% complete and the larger Kankakee Street Bridge project set to go out for bid in July. The Road District also reported that only 2.5 miles of gravel roads remain in the township.
Township Road Projects Key Points:
-
The Baker Road Bridge construction is 45% finished.
-
The Kankakee Street Bridge project will be put out for bid in July, with construction scheduled to begin in April 2026.
-
After removing Barton Road from the gravel system, the township now has only 2.5 miles of gravel roads left to maintain.
-
The Road District expects to receive a new truck in July.
Manhattan Township is making steady progress on its major infrastructure projects, Highway Commissioner Jim Baltas reported on Tuesday, June 10, 2025.
Baltas informed the township board that construction on the Baker Road Bridge is now 45% complete. This key project aims to replace an aging structure and improve transportation in the area.
Meanwhile, the township is preparing to move forward with another significant project. The Kankakee Street Bridge replacement will be put out for bid in July. Construction for this project is currently scheduled to begin in April 2026.
In his report, Baltas also noted a milestone in the road district’s long-term goal of reducing gravel roads. Barton Road has been converted from gravel, leaving only 2.5 miles of gravel roads remaining in the entire township. To aid in maintaining these roads, the district is also expecting the delivery of a new truck in July.
Community Events
Latest News Stories
Safety Upgrades Planned for Wilmington-Peotone Road; Gas Line Proposal Rejected
Manhattan Trustees Approve 2025 Property Tax Levy
Tensions Flare as Board Members Clash Over Budget Process and Protocol
Will County Board Approves $2.7 Million Reserve Draw to Finalize 0% Tax Levy
Manhattan-Elwood Library District Board Approves 2026-2030 Strategic Plan and Tax Levy
Manhattan Annexes Historic Round Barn Farm; Plans for Wedding Venue Move Forward
Jackson Township to Hear Proposal for Manure-to-Gas Energy Facility
Meeting Summary and Briefs: Manhattan School District 114 for November 12, 2025
Meeting Summary and Briefs: Lincoln-Way Community High School District 210 for November 20, 2025
Meeting Summary and Briefs: Manhattan Park Board for October 2025
WATCH: California starts portal for complaints about ICE
Trump signs drug treatment bill backed by Colorado representative