Manhattan Fire District Awards Initial Bids for New Station, Re-bids Four Items to Cut Costs

Spread the love

Article Summary:

The Manhattan Fire Protection District board approved most construction bids for its new fire station during a special meeting, but will re-bid roofing, flooring, overhead doors, and landscaping to reduce the project’s overall cost. A groundbreaking ceremony for the new facility, which will be financed by up to $8.75 million in bonds, is scheduled for July 31.

New Fire Station Project Key Points:

  • The board awarded bids for excavation, concrete, steel, HVAC, and other core construction trades.

  • Four components—roofing, flooring, overhead doors, and landscaping—will be re-bid to lower costs after initial proposals came in over budget.

  • Key changes include pricing a commercial asphalt shingle roof instead of steel and standard overhead doors instead of more expensive bi-fold doors.

  • A groundbreaking ceremony for the new station is set for July 31, with construction slated to begin in August.

MANHATTAN – The Manhattan Fire Protection District took a major step forward on its new fire station project Friday, awarding a dozen construction contracts while simultaneously launching a cost-cutting effort on four key components that drove initial bids over budget.

During a special meeting on July 11, the Board of Trustees, acting on the recommendation of construction manager ICI Builds, approved bids for essential trades including excavation, concrete, masonry, steel, plumbing, and electrical work. This allows the initial phases of the project to move forward, with a groundbreaking ceremony now planned for July 31 at 10:00 a.m.

However, after bids reviewed in June exceeded the district’s budget, officials will seek new proposals for roofing, flooring, overhead doors, and landscaping.

According to meeting documents, several changes are being made to the specifications for these items. The roof, originally planned as steel, will now be re-bid with a commercial asphalt shingle roof designed to withstand 100-mph winds, a point of clarification sought by Trustee Bob Davis. A steel roof will be included as a bid alternate.

The three large, bi-fold-style overhead doors facing Eastern Avenue will be re-bid as standard doors to reduce expense, with the more costly but safer bi-fold doors listed as an alternate. The original flooring plan, which included high-end epoxy, has also been modified. Finally, the landscaping bid was scaled back after initially covering all 21 acres of the site.

Chief Steve Malone was granted signature authority to execute the related documents. The board also approved a necessary addendum to its original contract with ICI Builds to reflect the revised bidding strategy.

The re-bid packages are expected to go out soon, with a bid opening scheduled for August 7. The board anticipates awarding the final four contracts at its August 18 meeting.

Latest News Stories

Illinois Quick Hits: $3M in taxpayer funds go to Chicago neighborhood center

Illinois Quick Hits: $3M in taxpayer funds go to Chicago neighborhood center

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois taxpayers have provided $3 million for a new neighborhood center on Chicago’s Southwest Side. Gov. J.B....
Lincoln Way West Warriors Baseball

Schulte’s Complete-Game Gem, Extra-Base Hits Lift Lincoln-Way West Past East 3-1

A dominant complete-game pitching performance by Kellen Schulte and a barrage of extra-base hits propelled the Lincoln-Way West varsity baseball team to a 3-1 conference victory over rival Lincoln-Way East...
Screenshot 2026-04-08 at 3.23.31 PM

Manhattan Board Greenlights ‘Pig in the Parking Lot’ 5K and Barbecue Event

Village of Manhattan Board of Trustees Meeting | April 7, 2026 Article Summary: A new family-friendly event combining a 5K race, a children's dash, and a community pig roast hosted...
Screenshot 2026-04-10 at 1.52.27 PM

Manhattan 114 Sets Committee of the Whole Schedule, Approves Key Administrative and Teaching Hires

Manhattan School District 114 Board of Education Meeting | April 8, 2026 Article Summary: To improve meeting efficiency and strategic planning, the Manhattan School District 114 Board of Education formalized...
Will County Board Graphic.03

Veterans Assistance Commission Buildout Complete, Body Scanner Installed at Juvenile Center

Will County Capital Improvements & IT Committee Meeting | April 7, 2026 Article Summary: The Will County Facilities Department announced the successful completion of the Veterans Assistance Commission (VAC) building...
Temu, Shein hit with class actions demanding tariff refunds

Temu, Shein hit with class actions demanding tariff refunds

By Jonathan Bilyk | Legal NewslineThe Center Square Online Chinese discount marketplace giants Temu and Shein have each been hit with nationwide class action lawsuits, demanding they repay customers for...
Illinois has most government units, but consolidation brings challenges

Illinois has most government units, but consolidation brings challenges

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – A new report says Illinois is among the most fragmented states in the nation when it comes...
Illinois quick hits: Southwest to lay off 107 as O'Hare service ends

Illinois quick hits: Southwest to lay off 107 as O’Hare service ends

By Jim Talamonti | The Center SquareThe Center Square Southwest to lay off 107 as O'Hare service ends According to an Illinois Worker Adjustment and Retraining Notification Act notice, 107...
State House passes 133 bills, many potential impacts for Illinoisans

State House passes 133 bills, many potential impacts for Illinoisans

By Sean Reed | The Center SquareThe Center Square (The Center Square) – The Illinois House of Representatives passed a total of 133 bills last week, sending them to the...
—Photo by Glenn P. Knoblock

Forest Preserve District Advances Major Extensions and Repairs on Plum Creek Greenway Trail in Crete Township

Article Summary: The Forest Preserve District is currently undertaking dual construction projects on the Plum Creek Greenway Trail, initiating a massive 1.5-mile southern extension through Plum Valley Preserve and commencing...
Packet_2026040714195175

Will County Survey Reveals Widespread AI Use as IT Drafts Governance Policy

Will County Capital Improvements & IT Committee Meeting | April 7, 2026 Article Summary: An internal survey revealed that nearly a dozen Will County departments are already utilizing Artificial Intelligence...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board for March 19, 2026

Will County Board Meeting | March 19, 2026 The Will County Board met on Thursday, March 19, 2026, to handle a diverse agenda that included heavy infrastructure spending, large-scale tax...
AARP_Fraud

AARP Urges Will County to Ban Cryptocurrency Kiosks Amid Exploding Senior Fraud Rates

Will County Board Legislative Committee Meeting | April 7, 2026 Article Summary: Representatives from AARP Illinois presented alarming new FBI data to the Will County Board Legislative Committee, revealing $11...
Will County Board Graphic.03

Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3...
Will County Board Graphic.01

Sunny Hill Nursing Home Implements Enhanced Infection Control and Safety Measures

Will County Public Health & Safety Committee Meeting | April 2, 2026 Article Summary: Sunny Hill Nursing Home has rolled out "enhanced barrier precautions" to prevent the spread of multi-drug...