Manhattan Fire District Awards Initial Bids for New Station, Re-bids Four Items to Cut Costs

Spread the love

Article Summary:

The Manhattan Fire Protection District board approved most construction bids for its new fire station during a special meeting, but will re-bid roofing, flooring, overhead doors, and landscaping to reduce the project’s overall cost. A groundbreaking ceremony for the new facility, which will be financed by up to $8.75 million in bonds, is scheduled for July 31.

New Fire Station Project Key Points:

  • The board awarded bids for excavation, concrete, steel, HVAC, and other core construction trades.

  • Four components—roofing, flooring, overhead doors, and landscaping—will be re-bid to lower costs after initial proposals came in over budget.

  • Key changes include pricing a commercial asphalt shingle roof instead of steel and standard overhead doors instead of more expensive bi-fold doors.

  • A groundbreaking ceremony for the new station is set for July 31, with construction slated to begin in August.

MANHATTAN – The Manhattan Fire Protection District took a major step forward on its new fire station project Friday, awarding a dozen construction contracts while simultaneously launching a cost-cutting effort on four key components that drove initial bids over budget.

During a special meeting on July 11, the Board of Trustees, acting on the recommendation of construction manager ICI Builds, approved bids for essential trades including excavation, concrete, masonry, steel, plumbing, and electrical work. This allows the initial phases of the project to move forward, with a groundbreaking ceremony now planned for July 31 at 10:00 a.m.

However, after bids reviewed in June exceeded the district’s budget, officials will seek new proposals for roofing, flooring, overhead doors, and landscaping.

According to meeting documents, several changes are being made to the specifications for these items. The roof, originally planned as steel, will now be re-bid with a commercial asphalt shingle roof designed to withstand 100-mph winds, a point of clarification sought by Trustee Bob Davis. A steel roof will be included as a bid alternate.

The three large, bi-fold-style overhead doors facing Eastern Avenue will be re-bid as standard doors to reduce expense, with the more costly but safer bi-fold doors listed as an alternate. The original flooring plan, which included high-end epoxy, has also been modified. Finally, the landscaping bid was scaled back after initially covering all 21 acres of the site.

Chief Steve Malone was granted signature authority to execute the related documents. The board also approved a necessary addendum to its original contract with ICI Builds to reflect the revised bidding strategy.

The re-bid packages are expected to go out soon, with a bid opening scheduled for August 7. The board anticipates awarding the final four contracts at its August 18 meeting.

Latest News Stories

Will County Board Graphic.02

Executive Committee Advances Dissolution of Southeast Joliet Sanitary District

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: The Executive Committee moved forward with two resolutions to facilitate the dissolution of the Southeast Joliet Sanitary District...
Will County Board Graphic.01

Meeting Summary and Briefs: Will County Board Legislative Committee for January 6, 2026

Will County Board Legislative Committee Meeting | January 6, 2026 Overall Meeting SummaryThe Will County Board Legislative Committee met on Tuesday, January 6, 2026, to finalize the county’s state and...
Will County Logo Graphic

Meeting Summary and Briefs: Capital Improvements & IT Committee for January 6, 2026

Capital Improvements & IT Committee Meeting | January 6, 2026 Overall Meeting SummaryThe Will County Board Capital Improvements and IT Committee met on Tuesday, January 6, 2026, to discuss facility...
Will County Board Graphic.04

Public Works Committee: $18.8 Million Contract Awarded for Lorenzo Road Bridge Over BNSF Railway

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: A contract for nearly $18.9 million was confirmed for the construction of a new bridge carrying...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for January 7, 2026

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Overall Meeting SummaryThe Will County Board Public Health and Safety Committee met on Wednesday, January 7, 2026,...
Will County Board Graphic.03

Executive Committee: Relaxes Rules for Retiring Employee Proclamations

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: The Executive Committee voted to amend county board rules to allow proclamations honoring retiring county employees to pass...
Will County Board Graphic.02

Lobbyist Updates: State Session Resumes; Transit Safety Concerns Raised

Will County Board Legislative Committee Meeting | January 6, 2026 Article Summary: State lobbyists briefed the Will County Legislative Committee on the upcoming General Assembly session, noting a likely focus...
Will County Finance Logo

Meeting Summary and Briefs: Will County Board Finance Committee for January 6, 2026

Will County Board Finance Committee Meeting | January 6, 2026 Meeting SummaryThe Will County Board Finance Committee met on Tuesday, January 6, 2026, to handle a light agenda of routine...
Will County Board Graphic.04

Capital Imp Committee: Facilities Director Reports on VAC Progress and Critical Health Department Elevator Repairs

Capital Improvements & IT Committee Meeting | January 6, 2026 Article Summary:Facilities Director Bill Fern provided updates on major renovation projects, including the completion of the Court Annex and the...
Will County Board Graphic.01

‘Good Food For All’ Initiative Proposes Local Agricultural Asset Mapping for Will County

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Article Summary: Bob Heuer of HNA Networks presented a "Good Food For All" initiative to the Public...
Will County Board Graphic.03

Public Works Committee Advances $3.2 Million Engineering Contract for Mills Road Reconstruction

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: The committee forwarded a resolution to award a $3.2 million contract to HDR Engineering, Inc. for...
Will County Board Graphic.04

Board Members Debate “Commitment to Truth” in Media Resolution

Will County Board Legislative Committee Meeting | January 6, 2026 Article Summary: A proposal to demand the reinstatement of the "Fairness Doctrine" for news media sparked a philosophical debate on...
Will County Board Graphic.01

Executive Committee: Speaker VanDuyne and Member Butler Clash Over Removal of Committee Chair

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: A heated exchange erupted during the January 8 Executive Committee meeting when Member Daniel Butler challenged Speaker Joe...
Will County Finance Logo

Finance Committee: County Appropriates Fees from $25 Million Wilmington Warehouse Project

Will County Board Finance Committee Meeting | January 6, 2026 Article Summary: The Finance Committee approved the appropriation of an administrative fee tied to a major industrial renovation in Wilmington....
will county board meeting.6

Capital Imp Committee: Begins Drafting Policy to Regulate Artificial Intelligence in County Government

Capital Improvements & IT Committee Meeting | January 6, 2026 Article Summary:The Will County Board Capital Improvements and IT Committee began formulating a comprehensive policy regarding the use of Artificial...