Kankakee Bridge Project Out for Bid at $1.6 Million, Baker Road Bridge Nears Completion
Manhattan Township Meeting | July 2025
Article Summary: Manhattan Township is moving forward with two significant infrastructure projects, with the Kankakee Bridge reconstruction now out for bid at an estimated cost of $1.6 million. Meanwhile, the Baker Road Bridge reconstruction project is more than halfway complete, according to a report from the Highway Commissioner.
Township Bridge Projects Key Points:
-
The Kankakee Bridge reconstruction project is now accepting bids, with the bid opening scheduled for July 16.
-
The estimated cost for the Kankakee Bridge project is $1.6 million.
-
Work on the Baker Road Bridge reconstruction is currently 55% complete.
Manhattan Township is advancing two major bridge reconstruction projects, with one heading to bid for $1.6 million and another already past the halfway point of construction, the township board learned on Tuesday, July 8, 2025.
In his monthly report, Highway Commissioner Jim Baltas announced that the Kankakee Bridge reconstruction project is now officially out for bid. The bid opening is scheduled for July 16, with the project carrying an estimated price tag of $1.6 million. This marks a critical step in moving the long-planned infrastructure upgrade toward the construction phase.
Baltas also provided a positive update on the Baker Road Bridge project, reporting that the reconstruction is now 55% complete. The project has been underway for several months and is progressing on schedule, aiming to restore a key local transportation link for residents. Both projects represent a significant investment in maintaining and improving the township’s rural road and bridge network.
Community Events
Latest News Stories
Fire District Maintains Strong Call Volume, Equipment Readiness
Golf Carts Not Permitted on Township Roads, Supervisor Clarifies
Meeting Briefs: Frankfort Township Board for May 19, 2025
Fire District May 19 Board Meeting Briefs
Will County Board Rejects Two Solar Farm Projects After Heated Public Opposition
County Approves $15 Million Water System Takeover for Southeast Joliet Area
Board Postpones County Purchasing Code Overhaul Amid Union Contractor Debate
New Frankfort Square Park Board Takes Helm Amid Strong Financials, Maksymiak and Moore Elected Leaders
Animal Permit Hearing Reveals Neighborhood Disputes Over Horses, Roosters in Crete Township
Park District Awards Eight Scholarships to Lincoln-Way East Seniors
Transportation Projects Advance as Board Approves Vision Zero, Road Improvements
Health Department Receives Budget Boost, Sunny Hill Admission Policy Updated