Manhattan Eyes Major Water and Sewer Rate Hikes to Fund Over $50 Million in Infrastructure Projects

Spread the love

Article Summary: To address aging infrastructure and prepare for significant future growth, Manhattan officials are planning more than $50 million in crucial water and sewer system upgrades, which will necessitate a series of rate increases for residents over the next several years.

Manhattan Village Board Finance Workshop Key Points:

  • Future projects include a new $6 million water tower and a $42.6 million expansion of the wastewater treatment plant.

  • A proposed multi-year rate increase would begin with a $1.65 hike in the water usage rate on Jan. 1, 2026, followed by further increases in subsequent years.

  • Officials state the upgrades are necessary to replace 20-year-old equipment, accommodate a projected population of 20,000 by 2050, and meet stricter IEPA regulations.

MANHATTAN – Village officials are preparing for a massive, multi-year overhaul of Manhattan’s water and sewer infrastructure, a plan carrying a price tag of more than $50 million that will require gradual rate increases for residents to fund.

The scope of the necessary projects was detailed during a Village Board Finance Workshop on September 9. Mayor Mike Adrieansen said the workshop’s purpose was to review major improvements required within the next five years to ensure the village’s infrastructure remains reliable.

“After careful analysis with the Public Works Department and Finance Department, it’s necessary to increase water and sewer rates and certain fees,” Mayor Adrieansen said, proposing that the rate hikes be spread over three years to lessen the impact on residents.

The proposed projects include a new Public Works facility (

6million),anewwatertowerforWell7(

6 million), and a comprehensive expansion of the well water treatment plant estimated to cost $42.6 million. These are in addition to the ongoing $9.7 million project for the Well 7 treatment and radium removal facility.

Dan Small of Strand Associates, the village’s engineering consultant, explained that growth is a major driver for the upgrades. The village’s 2025 Comprehensive Plan projects a population of 20,000 by the year 2050, which will require the wastewater treatment plant’s capacity to double from its current 1.35 million gallons per day (MGD) to 2.7 MGD.

However, Small noted that growth is not the only factor. “The last project was in 2005 and the mechanicals are going to need to be replaced soon,” he said. “The mechanicals are about twenty years old and that is about the shelf life before items start breaking down.”

The expansion will also address new regulatory requirements from the Illinois Environmental Protection Agency (IEPA), which is reducing the allowable limit for phosphorus in treated wastewater.

To fund the bonds for these large-scale projects, the village is proposing a multi-step increase in utility rates. The plan includes a $1.65 increase in the water usage rate starting January 1, 2026, followed by annual increases of $0.61 for the next three years. The sewer rate would see a proposed increase of $1.31 each year, beginning in 2027 for three years. Officials noted these figures could be adjusted if grant funding is secured.

Leave a Comment





Latest News Stories

Village of Manhattan Logo Graphic

Manhattan Swears In New Officials, Tables Fire Code Discussion

Village postpones St. Joseph's school sprinkler decision as benefactors emerge to help with costs Mayor Mike Adrieansen began his second term alongside newly elected Village Clerk Rebecca Bouck and trustees...
Village of Manhattan Logo Graphic

Manhattan Honors Departing Officials at Final Board Meeting

Beemsterboer, Adamski and Lewis recognized for combined 32 years of public service The Village of Manhattan honored three departing officials Tuesday evening, recognizing their combined 32 years of public service...
Village of Manhattan Logo Graphic

Manhattan Village Board Meeting Briefs

New Police Vehicles Approved: The village board authorized purchasing two new police interceptors for $157,362 total. A 2025 Ford F-150 will replace squad 773 for truck enforcement duties, while a...
MFPD-Logo-Fire District

Fire District Approves Construction Manager for New Station, Targets May 5 Bid Opening

The Manhattan Fire Protection District selected ICI Build as its construction management company for the new fire station project and is targeting May 5 for opening construction bids. The board...
MFPD-Logo-Fire District

Fire District Expands Health Programs, Considers Cancer Screening

The Manhattan Fire Protection District is expanding its employee wellness initiatives with potential cancer screening through body scans and continuing its successful injury prevention program. The Health and Safety Committee...
MFPD-Logo-Fire District

Fire District May 21 Meeting Briefs

Policy Manual Nearly Complete: The district's operational procedures and policy manual is 95% complete, with attorney review and union input ongoing. The complete manual will be presented to the board...
lincoln way school district

Lincoln-Way Board Approves Up to $31.3 Million Bond Sale for Safety, Security Upgrades

The Lincoln-Way Community High School District 210 Board of Education unanimously approved a resolution to issue up to $31.33 million in life safety bonds to fund a wide range of...
frankfort-square-park-district.2

Frankfort Square Park District Approves Budget Amid County Tax Adjustment, Funds Major Projects

The Frankfort Square Park District Board of Commissioners unanimously approved its operating budget for the 2025-2026 fiscal year during its April 17 meeting, earmarking funds for major ongoing projects and...
default

Lincoln-Way School Board Certifies Election, Re-elects Janik as President

The Lincoln-Way Community High School District 210 Board of Education officially reorganized for the upcoming year during its meeting on April 17, certifying the results of the April 1 consolidated...
lincoln way school district

New Electricity Contract to Save Lincoln-Way Over $500,000 Next Year

Lincoln-Way High School District 210 is poised for significant energy cost savings after the Board of Education unanimously approved a new 54-month electric commodity contract with Direct Energy. The agreement,...
frankfort-square-park-district.1

Four New Commissioners to Join Frankfort Square Park District Board in May

Four newly elected commissioners are set to join the Frankfort Square Park District Board in May, following the April 1, 2025, Consolidated Election. Executive Director Audrey Marcquenski formally congratulated Lauren...
Meeting Briefs

Meeting Briefs: Frankfort Square Park District for April 17, 2025

The Frankfort Square Park District Board of Commissioners met on April 17 to approve its annual budget, discuss new projects, and hear departmental updates. The district approved a nearly $5...
lincoln way school district.3

Lincoln-Way District 210 Board Briefs

District Finances Stable in March ReportAssistant Superintendent Michael Duback presented the Treasurer’s Report for the month ending March 31, 2025. Revenues for the month totaled $3.1 million, while expenditures were...
Frankfort-Township-Logo-Graphic

Frankfort Township Board Unanimously Opposes Government Consolidation

The Frankfort Township Board on Monday took a firm stance against a perennial issue in Illinois politics, unanimously passing a resolution to formally oppose any legislative efforts to consolidate or...
Frankfort-Township-Logo-Graphic

Frankfort Township Upgrading Senior Apartments Amidst High Demand

Frankfort Township is moving forward with significant upgrades to its senior apartments to meet modern standards, Supervisor Nick George announced at Monday’s board meeting. The improvements come as the township...