Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited “ongoing uncertainty regarding federal renewable energy policy” as a cause for delay. The extension for the Pralle Farms Partnership project on West Kennedy Road pushes its deadline to February 2026.

Peotone Solar Farm Extension Key Points:

  • Project: A commercial solar farm by Pralle Farms Partnership on West Kennedy Road in Peotone Township.

  • Action: The board approved a second 180-day extension for the project’s special use permit, now valid until February 8, 2026.

  • Reason: The developer cited delays related to new federal renewable energy legislation, referred to as the “One Big Beautiful Bill.”

  • Vote: The extension was approved 19-1, with board member Katie Deane-Schlottman voting against the measure.

JOLIET — Citing “ongoing uncertainty regarding federal renewable energy policy,” developers of a commercial solar farm in Peotone Township were granted a second extension on their special use permit by the Will County Board on Thursday.

The project, located on a vacant property on West Kennedy Road and owned by Pralle Farms Partnership, was initially approved on March 16, 2023. Developer Trajectory Energy Partners received its first extension in February 2025.

In a memo to the board’s Land Use and Development Committee, Marguerite Kenny, a county Zoning Administrator, noted that the applicant submitted the second extension request on August 6, 2025. The request “provided a detailed letter further explaining the current federal regulation climate” following the passage of new legislation in July referred to as the “One Big Beautiful Bill.”

A building permit for the solar facility was created on March 7, 2025, but the application is still under review and awaiting required submittals, according to the memo. Special use permits typically expire after two years if construction is not lawfully established.

The board approved the second 180-day extension in a 19-1 vote, with Katie Deane-Schlottman casting the lone dissenting vote. The permit is now valid through February 8, 2026, giving the developers more time to navigate the federal policy landscape and finalize their construction permit.

Leave a Comment





Latest News Stories

Two National Guard members shot near White House

Two National Guard members shot near White House

By Sarah Roderick-Fitch and Morgan SweeneyThe Center Square Two National Guard members from West Virginia were shot Wednesday afternoon near the White House, the state's governor confirmed. Gov. Pat Morrisey...
Trump election interference case in Georgia dismissed

Trump election interference case in Georgia dismissed

By Kim JarrettThe Center Square Election interference charges in Georgia against second-term Republican President Donald Trump were motioned for dismissal Wednesday by the Prosecuting Attorney's Council. In response, the president...
New park fee for foreign tourists could generate hundreds of millions

New park fee for foreign tourists could generate hundreds of millions

By Thérèse BoudreauxThe Center Square The Trump administration announced it is raising prices for nonresidents visiting national parks, a move that worries some tourism advocates but could generate hundreds of...
CDL proposals focus on safety as American truckers lose jobs, wages

CDL proposals focus on safety as American truckers lose jobs, wages

By Alan WootenThe Center Square Rising scrutiny of 194,000 state-issued nondomiciled CDLs to foreign workers with poor English language proficiency reveal two routes to safety. Rule change is one, done...
Trump's proposed $2,000 tariff rebates face costly challenges

Trump’s proposed $2,000 tariff rebates face costly challenges

By Brett RowlandThe Center Square President Donald Trump's plan to send some Americans $2,000 checks from the federal government's tariff collections is expected to cost more than the import duties...
Trump's legal fees could fall on the backs of Fulton County taxpayers

Trump’s legal fees could fall on the backs of Fulton County taxpayers

By Kim JarrettThe Center Square A law signed by Georgia Gov. Brian Kemp in May could put legal fees in the Donald Trump election interference case on the backs of...
Revenues from energy production at $14.6B for 2025

Revenues from energy production at $14.6B for 2025

By Alton WallaceThe Center Square Energy production on federal lands and waters and in U.S. tribal areas generated $14.61 billion in government revenues in the 2025 fiscal year, according to...
IL congressman’s retirement announcement sparks calls for election fixes

IL congressman’s retirement announcement sparks calls for election fixes

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Common Cause Illinois is urging lawmakers to close what it calls an “anti-democratic” loophole after Rep....
WATCH: Trump calls Pritzker ‘fat slob;’ Talk of reviving progressive tax criticized

WATCH: Trump calls Pritzker ‘fat slob;’ Talk of reviving progressive tax criticized

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop shares highlights from...
Illinois quick hits: Man arrested for threating legislator; vigilance urged during shopping season

Illinois quick hits: Man arrested for threating legislator; vigilance urged during shopping season

By Jim Talamonti | The Center SquareThe Center Square Man arrested for threating legislator Illinois State Police Division of Criminal Investigation special agents have arrested a Chicago man on charges...
Will County Board Graphic.01

County Takes Over “Central Will” Dial-A-Ride in Major Consolidation

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved an intergovernmental agreement to absorb the "Central Will" Dial-A-Ride system into the county-wide "Access Will County"...
Screenshot 2025-11-21 at 1.05.10 PM

Manhattan Officials Praise IDOT’s ‘Swift Action’ on Route 52, Discuss Further Safety Measures

Manhattan Village Board Meeting | November 18, 2025 Article Summary:Manhattan Mayor Mike Adrieansen thanked the Illinois Department of Transportation for its quick response in adding safety measures at the Route...
manhattan park district graphic.1

Manhattan Park Board Rejects Site Plan Proposal, Halts Planning Over Cost Dispute

Manhattan Park Board Meeting | October 9, 2025 Article Summary: The Manhattan Park Board unanimously rejected a proposal for an architectural concept site plan from Arete Design Studio, effectively pausing...
Will County Board Graphic.02

Board Denies Appeal for “Tiny Home” RV Living in Crete

Will County Board Meeting | November 2025 Article Summary: The Will County Board voted 19-2 to uphold a denial of a temporary use permit for a recreational vehicle (RV) being...
Jackson Township Graphic.1 NEW

Jackson Township Board Notified of Proposal for 800-Acre Data Center

Jackson Township Board Meeting | October 2025 Article Summary: During the monthly report, township officials announced the receipt of a public notice regarding a massive proposal to construct a data center...