Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Manhattan School District 114 for October 8, 2025

Manhattan School District 114 Board Meeting | October 8, 2025 The Manhattan School District 114 board meeting on Wednesday, October 8, 2025, featured extensive public testimony from parents detailing significant...
Meeting Briefs

Meeting Summary and Briefs: Village of Manhattan for October 7, 2025

The Manhattan Village Board advanced over $1.38 million in water infrastructure projects at its meeting on Tuesday, October 7, 2025, awarding contracts for three major water main upgrades that will...
Screenshot 2025-10-17 at 3.15.09 PM

Regional Office of Education Highlights School Safety, New Learning Programs in Update

Will County Board Regular Meeting | October 16, 2025 Article Summary: Will County Regional Superintendent Dr. Lisa Caparelli-Ruff updated the County Board on key initiatives, including the installation of shooter-resistant window...
Screenshot 2025-10-17 at 11.24.23 AM

Lincoln-Way to Purchase New Buses, Add Smaller Vehicles to Address Driver Shortage

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Lincoln-Way District 210 plans to update its transportation fleet by purchasing 28 new gasoline-powered school buses, three activity buses,...
Screenshot 2025-10-17 at 3.14.41 PM

Will County Awards $10.4 Million Contract for Bell Road Widening Project

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board has approved a $10.4 million contract with P.T. Ferro Construction Co. for a major roadway widening...
The Wild Flowe rFarm

Green Garden’s Wildflower Farm Granted Second Extension for Rural Events Permit

Will County Board Regular Meeting | October 16, 2025 Article Summary: Bengston Land Management, LLC, operators of The Wildflower Farm in Green Garden Township, received a second 180-day extension from the...
Screenshot 2025-10-17 at 11.46.09 AM

Manhattan Seeks $250,000 State Grant for Safe Routes to School Program

Village of Manhattan Board Meeting - October 7, 2025 Article Summary: The Village of Manhattan is applying for a grant of up to $250,000 from the Illinois Department of Transportation's...
mental health awareness day bipolar disorder anxiety stress emot

Will County Board Compromises on Mental Health Levy, Approves $10 Million After Debate

Will County Board Regular Meeting | October 16, 2025 Article Summary: The Will County Board on Thursday, October 16, 2025, approved a $10 million tax levy for the Community Mental Health...
Screenshot 2025-10-17 at 11.31.38 AM

Lincoln-Way Board Honors Students with Perfect ACT Scores, Music Educator of the Year

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Lincoln-Way District 210 celebrated exceptional academic and faculty achievement by formally recognizing nine students who earned a perfect composite...
Screenshot 2025-10-17 at 11.59.49 AM

Manhattan 114 Reviews Fall Student Benchmark Data, Sees Strong Growth

Manhattan School District 114 Board Meeting | October 8, 2025 Article Summary: Manhattan School District 114's Director of Curriculum and Instruction presented the board with fall benchmark data, showing that...
Screenshot 2025-10-17 at 11.46.03 AM

Public Hearing for 41-Home Butternut Ridge South Subdivision Continued in Manhattan

Village of Manhattan Board Meeting - October 7, 2025 Article Summary: The Manhattan Village Board opened a public hearing for the annexation of the proposed Butternut Ridge South development but...
Screenshot 2025-10-17 at 3.14.53 PM

Will County Board Rejects Proposed Tax Hike, Approves 0% Levy Increase in Contentious Vote

Will County Board Regular Meeting | October 16, 2025 Article Summary: In a significant move providing relief to taxpayers, the Will County Board on Thursday, October 16, 2025, voted to approve...
Screenshot 2025-10-17 at 11.32.04 AM

Lincoln-Way Support Staff Union Rejects Tentative Contract Agreement

LW210 Board of Education Meeting | October 16, 2025 Article Summary: Members of the Lincoln-Way Community High School District 210 support staff union have voted down a tentative five-year contract...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for October 7, 2025

The Will County Legislative Committee held a long and contentious meeting on Tuesday, October 7, 2025, highlighted by the narrow 4-3 passage of a controversial resolution supporting protections for immigrant...
Screenshot 2025-10-17 at 11.59.44 AM

Parents, Mayor Raise Concerns Over Special Education Services at Manhattan 114 Board Meeting

Manhattan School District 114 Board Meeting | October 8, 2025 Article Summary: Parents of a special needs student, supported by a statement from Manhattan's mayor, addressed the Manhattan School District...