Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

will-county-board.3

Will County Accepts $140,000 Developer Donation for Road Improvements

Will County's Public Works and Transportation Committee accepted a $140,143.90 donation from a developer in lieu of constructing traffic improvements along Laraway Road. The donation comes from the Lakes Park...
will-county-board.2

State Legislative Session Wrap-Up Shows Mixed Results

Will County's state legislative priorities saw mixed results as the Illinois General Assembly concluded its spring session on May 31, with several key bills advancing while others stalled. The Legislative...
will-county-board.2

Will County expands safety initiatives across facilities

Will County has implemented new safety protocols and training programs across its facilities, including the selection of department safety monitors and participation in community health education events. Each county department...
will-county-board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
MH VB 6-3

Village Releases $2.8 Million Letter of Credit for Completed Stonegate Subdivision

The Manhattan Village Board approved the release of a nearly $2.9 million letter of credit for the Stonegate subdivision after village engineers confirmed all required public improvements have been completed....
will-county-board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will-county-board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
MH VB 6-3

Kelly Gibbons Named Chairperson of Manhattan Planning and Zoning Commission

The Manhattan Village Board appointed Kelly Gibbons as chairperson of the Planning and Zoning Commission for a two-year term running through May 1, 2027. Gibbons, who already serves as a...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will-county-board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will-county-board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
Meeting Briefs

Manhattan Village Board Briefs

Banks Farm Development: The village board approved six separate resolutions demanding payment on letters of credit for various phases of the Banks Farm Development Villas of Prairie Trails project, covering...