Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Frankfort-Township-Logo-Graphic

Meeting Briefs: Frankfort Township Board for May 19, 2025

The Frankfort Township Board approved a 2.5% cost-of-living raise for its employees and discussed several major projects at its meeting on Monday, May 19. Supervisor Nick George announced that the...
MFPD-Logo-Fire District

Fire District May 19 Board Meeting Briefs

Board Actions Delayed: The swearing-in of new Trustee Mike Shivers was postponed until the next board meeting. The board voted to retain current leadership positions rather than reorganizing roles. Records...
Screenshot-2025-06-16-at-3.26.08-PM

Will County Board Rejects Two Solar Farm Projects After Heated Public Opposition

New Lenox area residents cite safety concerns, property values in opposing commercial solar facilities The Will County Board voted decisively against two proposed commercial solar energy facilities during its May...
will-county-board.3

County Approves $15 Million Water System Takeover for Southeast Joliet Area

700 homes to receive upgraded service as Joliet takes control of failing sanitary district The Will County Board voted 20-1 to support dissolving the Southeast Joliet Sanitary District and transferring...
will-county-board

Board Postpones County Purchasing Code Overhaul Amid Union Contractor Debate

Members seek clarification on requirements that could favor unionized businesses The Will County Board postponed action on proposed changes to county purchasing ordinances after members raised concerns about language that...
frankfort-square-park-district.2

New Frankfort Square Park Board Takes Helm Amid Strong Financials, Maksymiak and Moore Elected Leaders

The Frankfort Square Park District Board of Commissioners seated four new members and re-elected its leadership during a productive annual organizational meeting on May 15, all while celebrating a robust...
will-county-board.2

Animal Permit Hearing Reveals Neighborhood Disputes Over Horses, Roosters in Crete Township

Board postpones decision on Torres family request pending barn variance appeal A contentious hearing over Fernando Torres' request to keep horses on his Crete Township property exposed deep neighborhood divisions...
frankfort-square-park-district.1

Park District Awards Eight Scholarships to Lincoln-Way East Seniors

The Frankfort Square Park District awarded $1,000 scholarships to eight graduating seniors from Lincoln-Way East High School at the school’s Community Scholarship Night on May 7. Park Board Commissioners Frank...
will-county-board.3

Transportation Projects Advance as Board Approves Vision Zero, Road Improvements

County adopts traffic safety initiative while funding major infrastructure upgrades The Will County Board approved a comprehensive transportation agenda including adoption of Vision Zero principles and multiple road improvement projects...
County-Board-Room

Health Department Receives Budget Boost, Sunny Hill Admission Policy Updated

Board approves funding increases and policy changes for county health services The Will County Board approved budget appropriations for the health department and updated admission policies for Sunny Hill Nursing...
Meeting Briefs

Meeting Briefs: Frankfort Square Park District for May 15, 2025

At its annual organizational meeting, the Frankfort Square Park District Board of Commissioners swore in four members, re-elected its leadership, and reviewed its strong end-of-year financial report. The district’s funds...

Lincoln Way District 210 Achieves Highest Bond Rating in History

Lincoln Way Community High School District 210 has reached its highest-ever bond rating of AA3 from Moody's and A+ from Standard & Poor's, culminating a remarkable recovery from financial challenges...
Screenshot 2025-06-05 at 1.43.56 PM

District Recognizes Outstanding Student Readers in Statewide Program

Lincoln Way Community High School District 210 recognized exceptional students who completed the Read for a Lifetime program, with several achieving the rare distinction of reading 100 books over four...
Screenshot 2025-06-05 at 1.43.14 PM

Board Meeting Shorts

Budget Amendment Approved: The board approved amendments to the fiscal year 2025 budget totaling $121.7 million in revenue and $120.1 million in expenses. Changes primarily reflect bond proceeds and related...
Screenshot 2025-06-05 at 1.43.56 PM

Student Council Presidents Highlight Senior Year Accomplishments

Lincoln Way's three student council presidents delivered their final speeches of the school year, highlighting major accomplishments and memorable events before graduating this weekend. Jason Sro from Lincoln Way Central...