Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Screenshot 2025-06-05 at 1.43.56 PM

Student Council Presidents Highlight Senior Year Accomplishments

Lincoln Way's three student council presidents delivered their final speeches of the school year, highlighting major accomplishments and memorable events before graduating this weekend. Jason Sro from Lincoln Way Central...
Screenshot-2025-06-16-at-3.26.08-PM-1

Will County Board Meeting Briefs Package

COUNTY APPOINTMENTS Fire Protection District: Board approved county executive appointments to Manhattan Fire Protection District board. Agricultural Committee: Approved appointment to Agricultural Area Committee with Member Judy Ogala abstaining due...
Police blue and red flashing light on the car in the street

Manhattan Police Reports

On May 14th, at 1225 A.M. officers observed a vehicle traveling in the area of West North & Foxford at a high rate of speed. Officers radar indicated the gray...
Manhattan School District 114 Logo Graphic

Manhattan District Adopts New Math Program After Comprehensive Review

The Manhattan School District 114 Board of Education unanimously approved the adoption of Eureka Math Squared for kindergarten through eighth grade on Tuesday, concluding a year-long evaluation process involving 25...
Manhattan School District 114 Logo Graphic

Manhattan Junior High Scholastic Bowl Team Places Second at State Championship

Manhattan Junior High School's scholastic bowl team achieved a historic milestone by placing second in the state championship, marking the first time in the program's eight-year history that the team...
Manhattan School District 114 Logo Graphic

Enrollment Growth Prompts Staffing Discussions as Construction Continues

Manhattan School District 114 continues managing significant enrollment growth while construction projects remain on schedule for completion by the end of the school year. Current kindergarten enrollment of 218 students...
Manhattan School District 114 Logo Graphic

School District 114 Meeting Briefs

Budget Display Scheduled: The district's fiscal year 2025 amended budget will be on public display from May 15 through June 17, with board approval scheduled for the June 17 meeting....
Manhattan Township

Manhattan Road District Eyes $2.1M Budget, Hinges on Unguaranteed Solar Farm Funds

The Manhattan Township Road District is proposing a $2.15 million budget for the upcoming fiscal year, a plan that includes the purchase of a new truck and finishing a storage...
Manhattan Township

Manhattan Township Delays Decision on Critical Server Upgrade Amid Security Concerns

Manhattan Township officials are weighing a costly but necessary technology upgrade after learning their primary server is a decade old and runs on unsupported software, posing a potential cybersecurity risk....
frankfort-park-district.1

Frankfort Park District Reorganizes Board, Explores Options for Tax-Impacting Projects

FRANKFORT – The Frankfort Park District Board seated its re-elected members, reorganized its leadership, and approved its new annual budget on Tuesday, while also revealing it is actively exploring options...
Manhattan Township

Assessor Announces End to “Empathetic” Tax Reductions, Raises Senior Freeze Threshold

Manhattan Township homeowners will see two significant changes in property assessment rules, including the end of a long-standing practice of granting tax reductions for fire-damaged properties and a beneficial increase...
Manhattan Township

Meeting Briefs: Manhattan Township for May 13, 2025

Officials Sworn into Office: Clerk Kelly Baltas administered the oath of office to newly elected and re-elected officials. Taking the oath were Supervisor James F. Walsh and Trustees Eileen Fitzer, Paul...
frankfort-park-district

Aging Sara Park Building Poses Challenge for Park District

The Frankfort Park District is grappling with how to address the deteriorating Sara Park building, whose roof is in "bad shape" and whose location within a flood plain complicates any...
frankfort-park-district.1

Meeting Briefs: Frankfort Park District Board for May 13, 2025

The Frankfort Park District Board of Commissioners re-elected its leadership team for a new term and approved its fiscal year 2025-2026 budget at its meeting on Tuesday. The board also...
Village of Manhattan Logo Graphic

Manhattan Swears In New Officials, Tables Fire Code Discussion

Village postpones St. Joseph's school sprinkler decision as benefactors emerge to help with costs Mayor Mike Adrieansen began his second term alongside newly elected Village Clerk Rebecca Bouck and trustees...