Manhattan Fire District Awards Initial Bids for New Station, Re-bids Four Items to Cut Costs

Article Summary:

The Manhattan Fire Protection District board approved most construction bids for its new fire station during a special meeting, but will re-bid roofing, flooring, overhead doors, and landscaping to reduce the project’s overall cost. A groundbreaking ceremony for the new facility, which will be financed by up to $8.75 million in bonds, is scheduled for July 31.

New Fire Station Project Key Points:

  • The board awarded bids for excavation, concrete, steel, HVAC, and other core construction trades.

  • Four components—roofing, flooring, overhead doors, and landscaping—will be re-bid to lower costs after initial proposals came in over budget.

  • Key changes include pricing a commercial asphalt shingle roof instead of steel and standard overhead doors instead of more expensive bi-fold doors.

  • A groundbreaking ceremony for the new station is set for July 31, with construction slated to begin in August.

MANHATTAN – The Manhattan Fire Protection District took a major step forward on its new fire station project Friday, awarding a dozen construction contracts while simultaneously launching a cost-cutting effort on four key components that drove initial bids over budget.

During a special meeting on July 11, the Board of Trustees, acting on the recommendation of construction manager ICI Builds, approved bids for essential trades including excavation, concrete, masonry, steel, plumbing, and electrical work. This allows the initial phases of the project to move forward, with a groundbreaking ceremony now planned for July 31 at 10:00 a.m.

However, after bids reviewed in June exceeded the district’s budget, officials will seek new proposals for roofing, flooring, overhead doors, and landscaping.

According to meeting documents, several changes are being made to the specifications for these items. The roof, originally planned as steel, will now be re-bid with a commercial asphalt shingle roof designed to withstand 100-mph winds, a point of clarification sought by Trustee Bob Davis. A steel roof will be included as a bid alternate.

The three large, bi-fold-style overhead doors facing Eastern Avenue will be re-bid as standard doors to reduce expense, with the more costly but safer bi-fold doors listed as an alternate. The original flooring plan, which included high-end epoxy, has also been modified. Finally, the landscaping bid was scaled back after initially covering all 21 acres of the site.

Chief Steve Malone was granted signature authority to execute the related documents. The board also approved a necessary addendum to its original contract with ICI Builds to reflect the revised bidding strategy.

The re-bid packages are expected to go out soon, with a bid opening scheduled for August 7. The board anticipates awarding the final four contracts at its August 18 meeting.

Latest News Stories

will-county-board.2

Will County Approves Modified $756 Million Transportation Plan Despite Terminology Debate

Will County's Public Works and Transportation Committee approved a five-year, $756 million transportation improvement plan on June 3, but not before a heated debate over whether to call it a...
will-county-board.3

Will County completes major projects while others move forward

Will County's facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday. The Old Courthouse Plaza...
MH VB 6-3

Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Manhattan's Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final...
will-county-board.3

Will County Accepts $140,000 Developer Donation for Road Improvements

Will County's Public Works and Transportation Committee accepted a $140,143.90 donation from a developer in lieu of constructing traffic improvements along Laraway Road. The donation comes from the Lakes Park...
will-county-board.2

State Legislative Session Wrap-Up Shows Mixed Results

Will County's state legislative priorities saw mixed results as the Illinois General Assembly concluded its spring session on May 31, with several key bills advancing while others stalled. The Legislative...
will-county-board.2

Will County expands safety initiatives across facilities

Will County has implemented new safety protocols and training programs across its facilities, including the selection of department safety monitors and participation in community health education events. Each county department...
will-county-board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
MH VB 6-3

Village Releases $2.8 Million Letter of Credit for Completed Stonegate Subdivision

The Manhattan Village Board approved the release of a nearly $2.9 million letter of credit for the Stonegate subdivision after village engineers confirmed all required public improvements have been completed....
will-county-board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will-county-board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
MH VB 6-3

Kelly Gibbons Named Chairperson of Manhattan Planning and Zoning Commission

The Manhattan Village Board appointed Kelly Gibbons as chairperson of the Planning and Zoning Commission for a two-year term running through May 1, 2027. Gibbons, who already serves as a...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...