Manhattan Fire District Re-evaluating New Station Plans After Bids Come in Over Budget

Article Summary:

Construction bids for a new Manhattan Fire Protection District station have come in over the district’s maximum price, forcing officials to re-evaluate the project’s scope. Chief Steve Malone informed the Board of Trustees that the district is now working with its construction manager to identify cost-saving measures, a process that may require a special board meeting.

New Fire Station Project Key Points:

  • All submitted bids for the new fire station exceeded the district’s budget.

  • Chief Steve Malone said areas under review for cost reduction include roofing, insulation, HVAC, garage doors, and flooring.

  • A miscommunication regarding landscaping and property seeding is also being addressed.

  • The district is working with its construction manager, ICI Builds, to amend the project and control costs.

The Manhattan Fire Protection District is back to the drawing board on its new fire station project after construction bids came in higher than anticipated.

During the district’s board meeting on June 16, Fire Chief Steve Malone reported that the submitted bids all exceeded the project’s maximum budget. As a result, the district is now working with its construction manager, ICI Builds, to re-evaluate several components of the station’s design to bring costs back in line.

“New station bids have been received and came in over the max price, now we are looking to reevaluate a few things,” Malone told the board.

Among the areas being reviewed for potential savings are the station’s roofing, insulation, HVAC systems, garage doors, and flooring. Malone also noted there was a “miscommunication regarding seeding of the property” in the landscape bid that needs to be clarified. An addendum to the contract with ICI Builds will be required to reflect any changes.

Malone expressed hope that the review process would move quickly but acknowledged that the complexity of the issue might necessitate a special board meeting to approve a revised plan. The goal is to move forward without compromising the essential functions of the new facility.

In other business, Malone updated the board that the district is still awaiting the delivery of benches for the memorial site at Fire Station 83.

The Board of Trustees, including newly sworn-in member Mike Shivers, took the chief’s report under advisement. The district’s finances are otherwise in good shape, with accountant James Howard reporting that the budget is on track, interest rates on deposits are good, and real estate tax revenue is coming in as expected.

Latest News Stories

Wintrust-Crossroads-Sports-Complex

New Lenox Prepares for Grand Opening of Wintrust Crossroads Sports Complex

NEW LENOX – After months of anticipation and intensive work, the New Lenox Community Park District is making final preparations for the grand opening of its flagship Wintrust Crossroads Sports...
New-Lenox-School-122.2

New Lenox D122 Board Approves Tentative Budget, Sets September Public Hearing

The New Lenox School District 122 Board of Education has approved a tentative budget for the 2025-2026 fiscal year, maintaining its long-standing practice of balanced budgets funded by existing cash...
New-Lenox-Township-Food-Pantry

New Lenox Township Food Pantry Reports Record Demand in May

NEW LENOX – The New Lenox Township Food Pantry experienced a record level of need in May, serving 431 families and 1,107 individuals, according to a report at the June...
NL-VB-July-28

New Lenox to Dedicate Street Honoring Pope Leo XIV, Citing Deep Local Ties

NEW LENOX – The Village of New Lenox is celebrating its unique connection to the newly elected Pope Leo XIV, the first American to lead the Roman Catholic Church, by...
New-Lenox-School-122.7

D122 Renews Insurance Policies for Nearly $490,000

The New Lenox School District 122 Board of Education has renewed its property/casualty and worker's compensation insurance policies for the 2025-2026 school year, with total costs amounting to nearly $490,000....
new-lenox-township.2

New Lenox Township Addresses Cemetery Needs, Appoints New Liaison

NEW LENOX – New Lenox Township is turning its attention to the care and potential expansion of its cemeteries, an effort that will be spearheaded by a newly elected trustee....
New-Lenox-Village-Board.2

New Lenox Police Chief Louis Alessandrini Retires; Sgt. David Nykiel Promoted in Leadership Transition

NEW LENOX – The New Lenox Police Department is undergoing a significant leadership transition as Police Chief Louis Alessandrini retires after 20 years with the village, celebrated with an emotional...
Screenshot-2025-08-13-at-2.15.28-PM

Monee to Receive $250,000 Donation in Solar Project Agreement

Article Summary: The Village of Monee will receive a $250,000 donation from TPE IL W1202, LLC, after the Village Board authorized a community benefit agreement for a planned 5-megawatt solar...
new-lenox-park-district.6

New Lenox Park District Board Approves 2025-2026 Budget

NEW LENOX – The New Lenox Community Park District Board of Commissioners unanimously approved the budget and appropriation ordinance for the 2025-2026 fiscal year during its regular meeting on June...
New-Lenox-School-122.6

Staffing Shortage Leads D122 to Renew Contract for School Psychologist

Facing a persistent staffing shortage for a critical role, the New Lenox School District 122 Board of Education has renewed its contract with an outside agency to provide a school...
Meeting Briefs

Meeting Summary: New Lenox Township for June 12, 2025

At its June 12 meeting, the New Lenox Township Board of Trustees heard reports on rising demand for community services, discussed ongoing maintenance projects, and assigned responsibilities to its newly...
New-Lenox-Village-Board.4

New Lenox Approves Major Residential Subdivision, Paves Way for Route 6 Commercial Growth

NEW LENOX – The Village Board took decisive action on two major developments Monday, giving final approval to a 55-lot residential subdivision for "empty nesters" and clearing a key hurdle...
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-Sharons-Bay-Park

Contractor Selected for Sharon’s Bay Park Redevelopment

NEW LENOX – The New Lenox Community Park District is moving forward with plans to redevelop Sharon's Bay Park, having approved a contractor for the project at its Wednesday meeting....
New-Lenox-School-122.5

Handbook Changes at D122 Include Swapping PSAT for PreACT

Students in New Lenox School District 122 will see several changes in the upcoming school year, as the Board of Education approved updates to the 2025-2026 Parent/Student Handbook that affect...