Meeting Briefs

Meeting Briefs: Manhattan Township for March 11, 2025

Dial-A-Ride Service to be Absorbed by County: The Southwest Dial-A-Ride service is being absorbed by the larger Will County Dial-A-Ride service, which is offered through PACE. Township officials expressed hope that the consolidation will make the process of scheduling transportation services easier and more efficient for residents.

Property Tax Exemption Event Scheduled: The Will County Supervisor of Assessments Office will host an event to help residents apply for property tax exemptions on Monday, May 19, from 10:00 a.m. to 2:00 p.m. at the Township Community Hall. Representatives will be on hand to assist with applications for programs such as the Senior Freeze, Disabled Person, and Senior Homestead exemptions.

Highway Department Seeks Tar and Chip Bids: A bid notice for the highway department’s annual tar and chip road maintenance program has been published in the Peotone Vedette. The deadline for bid submission is March 21. The bids will be publicly opened at 5:00 p.m. on March 24 at the Road District Office. Progress is also continuing on the department’s new truck, for which the chassis has been delivered.

Township Investigates Unpermitted Storage Containers: The board is looking into large storage containers placed on a property at the corner of Rte. 52 and Cedar Road. Officials are not aware if a permit was issued for the containers by Will County. Clerk Kelly Baltas will file a Freedom of Information Act (FOIA) request with the county to determine if the proper steps were taken by the property owner.

Annual Town Meeting Preparations Finalized: The board unanimously approved the minutes and financial statement for the 2024 Annual Town Meeting. The approval was straightforward as there was no need to transfer funds between township accounts this year.

Latest News Stories

will-county-board.3

Will County completes major projects while others move forward

Will County's facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday. The Old Courthouse Plaza...
MH VB 6-3

Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Manhattan's Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final...
will-county-board.3

Will County Accepts $140,000 Developer Donation for Road Improvements

Will County's Public Works and Transportation Committee accepted a $140,143.90 donation from a developer in lieu of constructing traffic improvements along Laraway Road. The donation comes from the Lakes Park...
will-county-board.2

State Legislative Session Wrap-Up Shows Mixed Results

Will County's state legislative priorities saw mixed results as the Illinois General Assembly concluded its spring session on May 31, with several key bills advancing while others stalled. The Legislative...
will-county-board.2

Will County expands safety initiatives across facilities

Will County has implemented new safety protocols and training programs across its facilities, including the selection of department safety monitors and participation in community health education events. Each county department...
will-county-board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
MH VB 6-3

Village Releases $2.8 Million Letter of Credit for Completed Stonegate Subdivision

The Manhattan Village Board approved the release of a nearly $2.9 million letter of credit for the Stonegate subdivision after village engineers confirmed all required public improvements have been completed....
will-county-board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will-county-board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
MH VB 6-3

Kelly Gibbons Named Chairperson of Manhattan Planning and Zoning Commission

The Manhattan Village Board appointed Kelly Gibbons as chairperson of the Planning and Zoning Commission for a two-year term running through May 1, 2027. Gibbons, who already serves as a...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will-county-board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...