Road Contract Awarded as Township Races Against Bridge Funding Deadline
The Manhattan Township Highway Department has awarded a $91,000 contract for its annual road resurfacing program, while simultaneously facing a critical deadline that puts $500,000 in county funding for a major bridge project at risk.
At the April 8 township meeting, Highway Commissioner Jim Baltas announced that Steffens 3D Construction submitted the winning bid for this year’s tar and chip projects. The $91,000 price tag does not include the cost of stone, which the Road District will supply itself. To highlight rising costs, Commissioner Baltas noted that a similar project in 2016 cost only $36,000.
More urgently, the commissioner reported that the Kankakee Street Bridge replacement project is scheduled to go out for bids by July 16, 2025. If the bidding process is delayed beyond August 2025, the township will lose a $500,000 grant from Will County earmarked for the construction. The anticipated start date for the bridge work is spring 2026.
In other highway news, the demolition of the Baker Road Bridge began in early April as planned. The board approved the highway commissioner’s expenses as part of the finance report.
Latest News Stories
Contractor Selected for Sharon’s Bay Park Redevelopment
Contractor Selected for Sharon’s Bay Park Redevelopment
Handbook Changes at D122 Include Swapping PSAT for PreACT
New Dining Options Coming as Village Approves Hot Dog Stand, Restaurant Patio
Meeting Summary: New Lenox Park District for June 18, 2025
Monee Board Sets Spending Plan with 2025-2026 Appropriations Ordinance
New Lenox School District 122 Honors State Track and Field Athletes
Fiber Optic Internet Competition Coming to New Lenox
Monee Officials Issue Pool Safety Alert Amid Summer Heat
Village Board Approves Millions in Spending on Roads, Parks, and Museum
Meeting Summary: New Lenox School District 122 Board of Education for June 17, 2025
Meeting Summary: New Lenox Board of Trustees for July 28, 2025