Road Contract Awarded as Township Races Against Bridge Funding Deadline
The Manhattan Township Highway Department has awarded a $91,000 contract for its annual road resurfacing program, while simultaneously facing a critical deadline that puts $500,000 in county funding for a major bridge project at risk.
At the April 8 township meeting, Highway Commissioner Jim Baltas announced that Steffens 3D Construction submitted the winning bid for this year’s tar and chip projects. The $91,000 price tag does not include the cost of stone, which the Road District will supply itself. To highlight rising costs, Commissioner Baltas noted that a similar project in 2016 cost only $36,000.
More urgently, the commissioner reported that the Kankakee Street Bridge replacement project is scheduled to go out for bids by July 16, 2025. If the bidding process is delayed beyond August 2025, the township will lose a $500,000 grant from Will County earmarked for the construction. The anticipated start date for the bridge work is spring 2026.
In other highway news, the demolition of the Baker Road Bridge began in early April as planned. The board approved the highway commissioner’s expenses as part of the finance report.
Latest News Stories
New Lenox Fire District Secures $35,000 Grant for UTV in Solar Farm Agreement
Meeting Summary: New Lenox Fire Protection District for June 16, 2025
Meeting Summary and Briefs: Manhattan Township for June 2025
Kankakee Street Bridge Project to Go to Bid in July; Baker Road Bridge 45% Complete
Manhattan Township Donates $3,000 to Will County Community Concerns
New Lenox’s Crossroads Sports Complex Opens to Rave Reviews, On Time and Under Budget
New Lenox Waives Over $13,000 in Permit Fees for Park District, Church Projects