Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

WATCH: GOP governor candidates forum highlights; Pritzker talks taxes increase, Bears

WATCH: GOP governor candidates forum highlights; Pritzker talks taxes increase, Bears

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square's Greg Bishop provides highlights from Monday...
Illinois ‘RIFL’ act sparks fierce debate as lawmakers return to Springfield

Illinois ‘RIFL’ act sparks fierce debate as lawmakers return to Springfield

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – As Illinois lawmakers convene for the 2026 legislative session, House Bill 3320, Responsibility in Firearm Legislation...
SCOTUS declines to hear felony firearms cases

SCOTUS declines to hear felony firearms cases

By Andrew RiceThe Center Square The U.S. Supreme Court on Tuesday declined to take up two cases over whether individuals with felony records can be permanently disarmed under the Second...
Illinois Quick Hits: No injuries reported in Tuesday earthquake

Illinois Quick Hits: No injuries reported in Tuesday earthquake

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – No injuries have been reported after the U.S. Geological Survey reported a magnitude 3.8 earthquake near the...
One year in: Reviewing Trump's inaugural promises

One year in: Reviewing Trump’s inaugural promises

By Andrew RiceThe Center Square One year ago Tuesday, President Donald Trump told the nation its “golden age” had arrived, promising to spend his second term restoring stability at home...
lincoln-way-school-district.3-scaled-e1750128024313

Lincoln-Way Plans New Turf Field at Central and Courts at West for 2026

Lincoln-Way 210 Board of Education Meeting | Jan. 15, 2026 Article Summary: District 210 administrators presented a $4.5 million capital projects plan for Summer 2026, headlined by a new auxiliary...
Will County Board Graphic.04

Frankfort Township Road Commissioner Warns County Panel Against Low-Speed Vehicles

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee moved forward with a ban on low-speed vehicles on...
GOP hopefuls seek support, blast Pritzker at IL gubernatorial candidate forum

GOP hopefuls seek support, blast Pritzker at IL gubernatorial candidate forum

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – All four Illinois Republican gubernatorial candidates have no shortage of criticism for current Gov. J.B. Pritzker. 2022...
Illinois lawmaker questions IDHS over years-long data breach

Illinois lawmaker questions IDHS over years-long data breach

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – An Illinois lawmaker slammed the state agency as “incompetent” after the Department of Human Services revealed...
Will County Board Graphic.04

Draft County Federal Agenda Opposes Sharing Medicaid Patient Data with ICE

Article Summary: A proposed federal policy platform presented to the Will County Board takes a hard line against a federal agreement that allows Immigration and Customs Enforcement (ICE) to access...
Will County Logo Graphic

Northern Builders Development Brings Changes to Laraway and Gougar Roads in New Lenox

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board approved access permits for a new development by Northern Builders at the intersection of Laraway Road...
Manhattan School District 114 Logo Graphic

Manhattan 114 Approves Insurance Renewal Amidst Cost Increases

Manhattan School District 114 Meeting | Jan. 14, 2026 Article Summary: The Manhattan School District approved a renewal of its comprehensive insurance package despite a substantial increase in premiums. The...

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for January 6, 2026

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Meeting SummaryThe Will County Board Public Works & Transportation Committee met on Tuesday, January 6, 2026, to discuss...
Will County Board Graphic.03

County Board Debates Legislative Agendas; State Agenda Passes, Federal Agenda Sent Back

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board engaged in a vigorous and at times confusing debate over its 2026 legislative priorities, ultimately passing...
lincoln way school district 210 logo.1

District 210 Updates Online Course Policy and Increases Summer School Fees

Lincoln-Way 210 Board of Education Meeting | Jan. 15, 2026 Article Summary: The Board of Education approved an increase in summer school fees and clarified policies regarding online coursework for...