Eastern Avenue Road Project Moves Forward with Binder Installation, Final Phase Bidding Set

Spread the love

Manhattan’s Eastern Avenue reconstruction project will take another step forward this month as contractors prepare to install temporary road binder, while the village prepares to accept bids for the final phase of construction.

Village Engineer Mark reported to the board that two utility box covers have been completed on Eastern Avenue, allowing work to proceed to the next phase. Contractors will install four inches of binder to enable the road to reopen temporarily while the village finalizes plans for complete reconstruction.

“The two box covers are done, next they’re going to come in and they’re going to lay down 4 inches of binder so that we can go ahead and open the road,” Mark told trustees during Tuesday’s meeting.

The village will open bid proposals for the final Eastern Avenue reconstruction on June 26, with plans to award the contract at the July 1 village board meeting. The project timeline calls for completion by the end of September, though officials acknowledge weather and other factors could affect the schedule.

Village officials expect the bidding process to benefit from timing that avoids competition with Illinois Department of Transportation projects. “The guys that might not get a project with IDOT at the June letting are going to be looking for work, so that’s a good sign for us,” Mark explained.

Once the binder is installed, the village will maintain the temporary road surface as they have been doing with other portions of Eastern Avenue until full reconstruction begins. The road will need to be closed again during the final construction phase.

The Eastern Avenue project has been a significant undertaking for the village, with officials working to balance the need for infrastructure improvements with minimizing disruption to residents and businesses. The phased approach allows for continued access while ensuring proper utility work is completed before final road construction.

Village officials said the reconstruction should take approximately two months, though they emphasized that completion depends on weather conditions and contractor scheduling. The project represents a major infrastructure investment aimed at improving traffic flow and road conditions on one of Manhattan’s key thoroughfares.

The September completion target would finish the project before winter weather arrives, allowing for proper curing of new pavement and reducing the risk of weather-related delays.

Trustees expressed appreciation for the progress on the long-awaited project, which has required coordination between multiple contractors and utility companies to ensure all underground work is completed before final road reconstruction.

Latest News Stories

Illinois Quick Hits: Report says Pekin Bowling Center 'taxed out of business'

Illinois Quick Hits: Report says Pekin Bowling Center ‘taxed out of business’

By Jim Talamonti | The Center SquareThe Center Square Sunset Lanes in Pekin is set to close later this month as the bowling center’s owner says it is being “taxed...
Tiffany vows to end subsidies for data centers in Wisconsin

Tiffany vows to end subsidies for data centers in Wisconsin

By Jon StyfThe Center Square Wisconsin congressman and candidate for governor Tom Tiffany said that he will “end subsidies for data centers in Wisconsin” if he becomes governor. Tiffany was...
Screenshot 2026-03-29 at 4.44.29 PM

Public Works Secures $58,900 Valve Trailer, Seeks Federal Grants for Infrastructure

Village of Manhattan Meeting | March 16, 2026 Article Summary: The Manhattan Village Board authorized the purchase of a specialized $58,900 trailer to modernize water valve maintenance, while Public Works announced...
Screenshot 2026-05-05 at 1.39.16 PM

JJC Trustee Alleges Board Exclusion, Discriminatory Policies During Tense Meeting

Joliet Junior College Board of Trustees Meeting | March 11, 2026 Article Summary: Deep divisions on the Joliet Junior College Board of Trustees spilled into public view as Trustee Maureen Broderick...
Firefighter age bill stalled despite union backing

Firefighter age bill stalled despite union backing

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – A proposed Illinois bill aimed at addressing firefighter shortages by lowering the minimum hiring age has...
Will County Board Land Use Committee Graphic.3

County Board Members Pitch “Granny Flats,” Hobby Farm Zoning, and Farmland Mitigation in LRMP Brainstorm

Will County Board Land Use & Development Committee Meeting | March 26, 2026 Article Summary: During a brainstorming workshop for the county's new Land Resource Management Plan, Will County Board...
Screenshot 2026-03-29 at 4.21.41 PM

Meeting Summary and Briefs: Manhattan School District 114 for March 25, 2026

Manhattan School District 114 Meeting | March 25, 2026 The Manhattan School District 114 Board of Education held a special meeting on Wednesday, March 25, 2026, to address time-sensitive capital...
Hyundai Translead

Will County Board Approves Tax Abatement for $345 Million Hyundai Translead Project

Will County Board Meeting | March 19, 2026 Article Summary: The Will County Board has authorized an agreement of intent to abate taxes for a massive $345 million manufacturing project...
lincoln way school district 210 logo.2

Lincoln-Way 210 Advances Summer Site Improvements and Asbestos Abatement Projects

Lincoln-Way Community High School District 210 Meeting | March 19, 2026 Article Summary: The Board of Education approved an asbestos abatement contract and initial site improvement bids to prepare for...
Lawmaker criticizes surplus spending bill

Lawmaker criticizes surplus spending bill

By Catrina Baker | The Center Square contributorThe Center Square (The Center Square) – A proposal aimed at helping local governments manage retiree health care costs is drawing differing views...
Screenshot 2026-03-29 at 4.21.41 PM

Manhattan District 114 Board Abates $252,430 from 2025 Bond and Interest Levy

Manhattan School District 114 Meeting | March 25, 2026 Article Summary: Utilizing finalized property value estimates from the county, the Manhattan School District 114 Board of Education approved a levy abatement...
Screenshot 2026-03-29 at 4.44.29 PM

Manhattan Approves Estimated $1.1 Million Resurfacing Project for Leighlinbridge Subdivision

Village of Manhattan Meeting | March 16, 2026 Article Summary: The Village of Manhattan approved a state resolution to secure Motor Fuel Tax funding for a major road resurfacing project targeting...
Salvation Army rehab ‘enrollees’ who work at thrift stores aren’t ‘employees’

Salvation Army rehab ‘enrollees’ who work at thrift stores aren’t ‘employees’

By Jonathan Bilyk | Legal NewslineThe Center Square A few days after agreeing to let them proceed with their class action against one of America's most prominent charities under labor...
Illinois housing affordability efforts pit tax cuts against new spending

Illinois housing affordability efforts pit tax cuts against new spending

By Sean Reed | The Center SquareThe Center Square (The Center Square) – As homeownership may be growing out of reach for many young residents, Illinois lawmakers are split between...
Illinois Quick Hits: Chicago city workers owe more than $19M

Illinois Quick Hits: Chicago city workers owe more than $19M

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Chicago city workers reportedly owe more than $19 million in traffic tickets, water bills and fines, yet...