will-county-board.3

Will County completes major projects while others move forward

Spread the love

Will County’s facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday.

The Old Courthouse Plaza concrete replacement project at 14 W. Jefferson has been finished, with new picnic benches installed and the area fully restored with handicap-accessible ramps meeting current ADA standards, according to Facilities Director Bill Fern.

“The plaza is completely usable again, safe level, all new concrete, all handicap ramps all been replaced,” Fern told committee members during his monthly facilities update.

The county has also completed parking lot resurfacing at both the Community Health Center and River Valley Juvenile Detention Center. The River Valley project addressed serious deterioration issues and brought handicap ramps up to current ADA compliance standards after the original construction was determined to be too steep by today’s requirements.

“That parking lot was in serious need of resurfacing,” Fern said. “The handicap ramps, the ADA accessible areas when they built it were too steep to today’s standards, so now they are all compliant.”

Work continues on several other major projects across county properties. The Court Annex/State’s Attorney Level 2 renovations at 57 N. Ottawa are scheduled to begin construction July 10 following bid openings set for June 4. The project, which involves combining unused courtrooms on the second and third floors to create more usable space, is expected to be completed by fall 2025.

Similarly, Land Use/Public Defender renovations at 58 E. Clinton are progressing with Level 3 complete and Level 4 work beginning June 16. That project is also slated for completion in August.

The Veterans Assistance Commission buildout at 1300 Copperfield has reached several milestones, with roof replacement 95% complete and both glass replacement and interior renovations set to begin June 9. The project involves UV-coated, double-pane glass replacement and is expected to wrap up in fall 2025.

Committee Chair Mica Freeman noted the county is expecting facility assessment reports by month’s end that will merge facility condition evaluations with space needs analysis. The comprehensive assessment covers 75% of county-owned properties, with the largest facilities – Adult Detention Facility and River Valley – nearing completion of their evaluations.

Fern reported his team handled over 760 work orders in May, completing them with 98% on-time performance at an average cost of $19.75 per work order. The facilities team logged more than 800 hours of labor during the month.

“The team is really moving,” Fern said, highlighting the department’s productivity while maintaining zero workplace injuries – a safety record Committee member Herbert Brooks Jr. praised as worthy of celebration.

The committee also addressed ongoing courthouse issues, with scaffolding removal underway as stone replacement work continues. Water infiltration behind limestone panels caused damage when freezing temperatures expanded the moisture, pushing stones outward. Sixteen new quarried limestone pieces are being manufactured for replacement, with installation planned using swing stages rather than scaffolding.

A facilities report from material specialists examining the courthouse damage is expected by the end of next week, providing definitive analysis of the stone failure and remediation efforts.

The next committee meeting is scheduled for July 1.

Leave a Comment





Latest News Stories

Police Crime

County Board Authorizes Audit of Homer Glen Policing Contract; Officials Seek ‘True Cost’ of Services

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board unanimously approved a $75,000 contract to audit the cost of law enforcement services provided to the Village...
solar panels photovoltaics in solar farm

Soltage Drops Battery Storage Plans, Secures Extensions for Two Crete Solar Projects

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board granted second extensions to special use permits for two solar energy projects in Crete Township. The developer,...
Will County Board Graphic.02

Scrap Metal Drop-Off Near Mokena Approved by Single Vote

Will County Board Meeting | February 19, 2026 Article Summary: A contested proposal for an outdoor recyclable material drop-off facility in Frankfort Township passed by a single vote following objections from...
Will County Board Graphic.01

Landscape Business Approved on Cedar Road Despite ‘Dangerous Curve’ Concerns

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a special use permit for a landscape business on Cedar Road in Homer Glen, despite concerns...
Committee-Ad-Hoc.Graphic

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for February 10, 2026

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Meeting SummaryThe Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, February 10, 2026, to continue its comprehensive...
Committee-Land Use.Graphic

Meeting Summary and Briefs: Will County Land Use & Development Committee for February 5, 2026

Will County Land Use & Development Committee Meeting | February 5, 2026 The Will County Land Use and Development Committee met on Thursday, February 5, 2026, to deliberate on several...
Screenshot 2026-03-22 at 12.12.19 PM

Meeting Summary and Briefs: Manhattan School District 114 for February 11, 2026

Manhattan School District 114 Meeting | February 11, 2026 The Manhattan School District 114 Board of Education held its regular meeting on Wednesday, February 11, 2026, at 6:30 p.m. at...
Screenshot 2026-02-22 at 5.06.42 PM

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for February 18, 2026

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Meeting SummaryThe Joliet Junior College Board of Trustees met on Wednesday, February 18, 2026, for a regular meeting dominated...
Committee-Executive.Graphic

Meeting Summary and Briefs: Will County Executive Committee for February 11, 2026

Will County Executive Committee Meeting | February 11, 2026 Meeting SummaryThe Will County Board Executive Committee met on Wednesday, February 11, 2026, tackling a heavy agenda focused on economic development...
Screenshot 2026-02-22 at 4.29.56 PM

Advisory Committee Debates Rigor of Online Summer School Options

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The District 210 Advisory Committee reported on discussions regarding the potential expansion of online summer school offerings,...
Election Vote Graphic

Group Presents Allegations of 2024 Voter Roll Errors to County Board

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a resolution calling for the review of election systems and integrity, following public comments alleging inaccuracies...
manhattan fire district graphic logo.1

Manhattan Fire District Hires Three Full-Time Paramedics, Reports Progress on New Station

Manhattan Fire Protection District Meeting | Jan. 19, 2026 Article Summary: The Manhattan Fire Protection District Board authorized the immediate hiring of three firefighter/paramedics and prepared for a potential vacancy...
Will County Board Graphic.04

Will County Board Advised on Strict “Judicial” Role Ahead of Landfill Expansion Application

Will County Landfill Committee Meeting | February 10, 2026 Article Summary: During a detailed legal briefing on Tuesday, the Will County Landfill Committee received strict instructions regarding their conduct during...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Bath House Regulations Updated; Removes 60-Day Licensing Window

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee approved updates to the regulations governing bath houses and...
Committee-Land Use.Graphic

Land Use Committee Rejects Shorewood Solar Farm Despite 25-Year Lease Offer

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: The Will County Land Use and Development Committee voted against recommending a controversial solar farm proposal...