Solar Project Extensions Approved as Industry Faces Permitting Delays
Three solar energy projects received 180-day extensions from Will County’s Land Use & Development Committee Thursday as developers continue working through lengthy permitting processes with utility companies and other agencies.
The extensions cover projects in Peotone, Channahon, and Crete townships that received special use permits in 2023 but haven’t yet obtained building permits. Under county rules, special use permits expire within two years unless construction permits are issued.
A Peotone Township solar project by Turning Point Energy received its extension after experiencing delays with updated conservation plans and changing fire district requirements. Joseph Chessup, representing the developer, said soil and water conservation standards were updated last year, requiring them to restart their conservation planning process.
The Manhattan Fire Protection District also changed safety standards as recently as May 20, requiring wider access roads and higher weight capacity to accommodate 80,000-pound fire equipment.
“There’s been a few unexpected delays with getting the permits finalized for this project,” Chessup said.
Staff also provided an update on solar interconnection requirements after meeting with ComEd officials. The utility company clarified that they don’t require above-ground power connections for solar projects, contrary to claims made by some developers.
ComEd uses a five-step process taking about 180 days for interconnection agreements. While they typically install four riser poles for connections, they can accommodate underground lines for 12KV systems, though 34KV lines remain economically impractical to bury.
The committee expressed interest in requiring more underground infrastructure for future solar projects to preserve rural aesthetics. “I would like to see us have them put it underground as much as they possibly can,” said Committee member Judy Ogala.
Latest News Stories
WATCH: Chicago reacts to Trump’s public safety push; AI in schools; rural health care
Will County Board Approves New Fee Schedule for Recorder of Deeds
Illinois expands campus abortion access, shields doctors from legal risk
Illinois quick hits: Human trafficking enforcement; health care fraud division announced
Nonprofit files complaints against Trump attorneys but almost no public discipline
Jackson Township to Hear Proposal for Manure-to-Gas Energy Facility
Everyday Economics: Softer tape, PCE in focus, and the Fed’s next move
Meeting Summary and Briefs: Manhattan School District 114 Board of Education for August 13, 2025
Marine’s mother takes on troop transport duties for family visits
Trump plans to clean up Democrat-run cities over local objections
Will County Board Formally Opposes Heavier, Longer Trucks on National Roadways
Meeting Summary and Briefs: Manhattan Park Board for July 2025
School Board Debates Governance Structure, Tables Decision Until November
Energy advocate applauds oil and gas commingling updates