Solar Project Extensions Approved as Industry Faces Permitting Delays
Three solar energy projects received 180-day extensions from Will County’s Land Use & Development Committee Thursday as developers continue working through lengthy permitting processes with utility companies and other agencies.
The extensions cover projects in Peotone, Channahon, and Crete townships that received special use permits in 2023 but haven’t yet obtained building permits. Under county rules, special use permits expire within two years unless construction permits are issued.
A Peotone Township solar project by Turning Point Energy received its extension after experiencing delays with updated conservation plans and changing fire district requirements. Joseph Chessup, representing the developer, said soil and water conservation standards were updated last year, requiring them to restart their conservation planning process.
The Manhattan Fire Protection District also changed safety standards as recently as May 20, requiring wider access roads and higher weight capacity to accommodate 80,000-pound fire equipment.
“There’s been a few unexpected delays with getting the permits finalized for this project,” Chessup said.
Staff also provided an update on solar interconnection requirements after meeting with ComEd officials. The utility company clarified that they don’t require above-ground power connections for solar projects, contrary to claims made by some developers.
ComEd uses a five-step process taking about 180 days for interconnection agreements. While they typically install four riser poles for connections, they can accommodate underground lines for 12KV systems, though 34KV lines remain economically impractical to bury.
The committee expressed interest in requiring more underground infrastructure for future solar projects to preserve rural aesthetics. “I would like to see us have them put it underground as much as they possibly can,” said Committee member Judy Ogala.
Latest News Stories
An ‘arms race’ for pay at elite, tax-exempt colleges
Inflation rises to 3.8%, driven by energy prices
New congressional map expected for Alabama in wake of high court ruling
Manhattan District 114 Explores Joint Community Survey for Fall Strategic Plan
State Legislative Update: Housing Mandates, Mega Projects, and Data Centers Prompt Local Control Concerns
Data center regs proposed as $20 billion, 795-acre Joliet project advances
Labor stats offer mixed bag for Illinois
Lawsuit: IL state VRA unconstitutionally lets Dems divide voters by race
Illinois Quick Hits: State grants offered to tackle ‘challenging’ properties
Officers mourn fallen Chicago cop as policy debate grows
Trump accuses Schumer of election ‘interference’ with New York task force
Poll site gun ban proposal draws pushback