Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion

Spread the love

Article Summary:

The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a mid-August occupancy following the recent installation of a long-delayed electrical panel.

Public Works Building Key Points:

  • Payment request #13 for $566,134.16 to Professional Building Services Inc. was unanimously approved.

  • The facility is nearing completion after a key electrical panel, which had been on back order, was installed this week.

  • Occupancy is anticipated by mid-August, with a grand opening to be scheduled at a later date.

MONEE — The Village of Monee’s new Public Works facility is nearing the finish line, with the Village Board approving another major payment for the project at its Wednesday meeting.

Trustees unanimously authorized pay request #13 in the amount of $566,134.16 to the project’s construction manager, Professional Building Services Inc. The payment covers work completed through July 10, including significant progress from contractors for concrete, masonry, general construction, and flooring.

Public Works Trustee Doug Horne provided a construction update, highlighting a critical milestone. “If you recall last time we met here, there was a discussion of a delayed electrical panel and it was on back order,” Horne said. “Well, I’m happy to report that that is being installed this week.”

With the panel in place, the factory startup of essential systems is scheduled for the week of July 28. A preliminary walkthrough for building staff is planned for the week of August 4.

“We’re hopeful to have occupancy of the building by mid-August,” Horne added. “The grand opening is yet to be scheduled. We’ll worry about that once it’s online.”

The payment request was reviewed and certified by the Farnsworth Group and village staff, who confirmed it met the project’s plans and specifications.

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 Board of Education for September 18, 2025

The Lincoln-Way Community High School District 210 Board of Education on Thursday, September 18, 2025, formally adopted a $172.7 million budget for the 2025-2026 school year. The budget includes a...
manhattan park district graphic.1

Manhattan Park Board Deadlocks on Paying for Sports Complex Plan, Motion Fails

Article Summary: A proposal for the Manhattan Park District to fund an architectural concept plan for a new sports complex failed to pass on Thursday, August 14, 2025, after a...
manhattan elwood library graphic.5

Manhattan-Elwood Library Board Adopts Annual Budget and Appropriation Ordinance

Article Summary: The Manhattan-Elwood Public Library District Board of Trustees has formally adopted its budget for the upcoming fiscal year following a public hearing. The approval of the combined Budget...
lincoln way school district 210 logo.1

Lincoln-Way 210 to Launch District Literacy Plan, Expands Community Partnerships

Article Summary: As part of its strategic plan, Lincoln-Way High School District 210 is developing a comprehensive literacy plan to embed critical thinking skills across the curriculum. The district is also...
Meeting Briefs

Meeting Summary and Briefs: Manhattan School District 114 Board of Education for September 17, 2025

The Manhattan School District 114 Board of Education heard emotional testimony from parents regarding serious transportation safety and timeliness issues at its Wednesday meeting. The board also formally approved the...
jackson township graphic.2

Jackson Township Refers Manure-to-Gas Plant Proposal to Planning Commission

Article Summary: Representatives for a company named Elwood81, LLC, presented a proposal for an anaerobic digestion facility to the Jackson Township Board. Following the presentation, the board directed the company...
WCO 2025-09-27 at 9.05.04 AM

County Board Abates Over $25 Million in Property Taxes for Bond Payments

Article Summary: Will County property taxpayers will be spared over $25 million in taxes for the 2026 payment year after the County Board voted to abate taxes for six separate...
Manhattan School District 114 Logo Graphic

School Board Approves ‘Board Book Premier’ for Paperless Meetings

Article Summary: The Manhattan School District 114 will transition to a digital platform for its board meetings, selecting Board Book Premier to improve public access to documents and create a...
Screenshot

Lincoln-Way 210 Prepares for “Retirement Wave” with Focus on Recruitment

Article Summary: Lincoln-Way High School District 210 is bracing for a significant number of retirements, with 47 teachers expected to leave over the next four years, representing nearly a quarter of...
Press Plus

District 114 to Overhaul Policy Updates with New ‘Press Plus’ Service

Article Summary: Manhattan School District 114 is moving forward with Press Plus, a service from the Illinois Association of School Boards designed to streamline and modernize the updating of its...
lincoln way school district 210 logo.2

Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings

Article Summary: The Lincoln-Way District 210 board is considering a 20-year agreement to participate in a state-sponsored community solar program that could save the district an estimated $155,000 annually on electricity...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025

Joliet Junior College Board of Trustees Meeting | September 2025 The Joliet Junior College (JJC) Board of Trustees approved a landmark agreement with the City of Joliet to explore a...
manhattan park district graphic.2

Manhattan Park Board Hires New Architect for Round Barn Buildout, Secures Annexation for Future Banquet Hall

Article Summary: The Manhattan Park Board advanced its plans for the historic Round Barn Farm on Thursday, August 14, 2025, by hiring a new design firm for a partial interior...
Screenshot

Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases

Article Summary: The Lincoln-Way Community High School District 210 Board of Education approved the Fiscal Year 2026 budget, which includes a planned operating deficit of $814,000 to accommodate the purchase of...