Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion
Article Summary:
The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a mid-August occupancy following the recent installation of a long-delayed electrical panel.
Public Works Building Key Points:
-
Payment request #13 for $566,134.16 to Professional Building Services Inc. was unanimously approved.
-
The facility is nearing completion after a key electrical panel, which had been on back order, was installed this week.
-
Occupancy is anticipated by mid-August, with a grand opening to be scheduled at a later date.
MONEE — The Village of Monee’s new Public Works facility is nearing the finish line, with the Village Board approving another major payment for the project at its Wednesday meeting.
Trustees unanimously authorized pay request #13 in the amount of $566,134.16 to the project’s construction manager, Professional Building Services Inc. The payment covers work completed through July 10, including significant progress from contractors for concrete, masonry, general construction, and flooring.
Public Works Trustee Doug Horne provided a construction update, highlighting a critical milestone. “If you recall last time we met here, there was a discussion of a delayed electrical panel and it was on back order,” Horne said. “Well, I’m happy to report that that is being installed this week.”
With the panel in place, the factory startup of essential systems is scheduled for the week of July 28. A preliminary walkthrough for building staff is planned for the week of August 4.
“We’re hopeful to have occupancy of the building by mid-August,” Horne added. “The grand opening is yet to be scheduled. We’ll worry about that once it’s online.”
The payment request was reviewed and certified by the Farnsworth Group and village staff, who confirmed it met the project’s plans and specifications.
Latest News Stories
Construction Progresses on New Manhattan Fire Station, August Completion Anticipated
Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone
Will County Advances Nearly $1.5 Million in Right-of-Way and Improvement Agreements for Weber, Gougar, and Laraway Roads
Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township
Will County Board Backs $10 Million State Public Health Grant Increase Amid Funding Cuts
Barn Fire on Whispering Hills Lane Claims Livestock, Draws Extensive Mutual Aid Response
Will County Public Works Committee Shelves License Plate Reader Agreement Amid Bipartisan Privacy Concerns
Will County Planning and Zoning Commission Overrides Staff to Approve New Lenox Accessory Building Variance
Will County Sheriff’s Office Welcomes Remi, First Electronic Scent Detection Dog
Will County Transportation Department Announces Open House for Manhattan-Monee Road Expansion
Will County Community Mental Health Board Faces $5 Million Shortfall in 2026 Grant Requests
Meeting Summary and Briefs: Public Health & Safety Committee for March 5, 2026
Will County Officials Warn of Zoom Court Scam Targeting Defendants for Fraudulent Dismissal Fees