Key Stretch of Bell Road on Track for Thanksgiving Reopening, Committee Approves Additional Funds
ARTICLE SUMMARY Construction on Bell Road between 159th and 151st Streets is scheduled to have all lanes open by Thanksgiving, officials announced as the Public Works & Transportation Committee approved a $652,896 supplemental contract for engineering services.
Key Points:
-
The Thanksgiving target for reopening all lanes was confirmed by Director of Transportation Jeff Ronaldson.
-
The supplemental agreement with AECOM Technical Services, Inc., is for continued construction engineering oversight as the project extends due to utility conflict delays.
JOLIET—Commuters navigating construction on Bell Road received good news Tuesday, as Will County’s transportation director announced that all lanes on the key stretch between 159th Street and 151st Street are expected to be open by Thanksgiving.
The update came as the Will County Public Works & Transportation Committee approved a supplemental professional services agreement for $652,896 with AECOM Technical Services, Inc., for continued construction engineering on the project.
“Essentially all lanes will be open by Thanksgiving,” Director of Transportation Jeff Ronaldson told the committee. He added that some minor work, such as landscaping and final surfacing, could carry over into the spring.
The contract extension with AECOM covers the cost of having the resident engineer and consulting firm oversee construction, which was extended due to delays caused by utility conflicts. The project involves the reconstruction and widening of the heavily traveled corridor in County Board District 4.
Board Member Steve Balich (R-Homer Glen) questioned Ronaldson about the timeline, noting that residents are “jumping up and down out there, which I get it.” Ronaldson confirmed the Thanksgiving target, solidifying the timeline for the much-anticipated reopening. The committee approved the supplemental agreement unanimously.
Latest News Stories
Health & Safety Committee: Opioid Overdose Deaths Drop to Zero in January as Behavioral Health Department Expands Role
State of the College: JJC Announces Plans for New Campus in Grundy County
Meeting Summary and Briefs: Manhattan Village Board for Feb. 3, 2026
Meeting Summary and Briefs: Public Works & Transportation Committee for February 3, 2026
Health & Safety Committee: District 3 Board Member Pushes for Expanded Animal Control Services in Monee, Crete
Meeting Summary and Briefs: Will County Capital Improvements & IT Committee for Jan. 6, 2026
Legislative Committee: Lobbyists Report on Federal Shutdown and Legislative Outlook
County Authorizes Financial Study of Homer Glen Law Enforcement Contract
Meeting Summary and Briefs: Joliet Junior College Board of Trustees Workshop for January 28, 2026
IDOT Implementing Speed Limit Changes in Manhattan
Will County Public Works Debates Future Bridge Needs as 159th Street Closure Looms
Capital Imp Committee: Veterans Assistance Commission Set to Move into New Facility