Manhattan Township Meeting | July 2025
Article Summary: Manhattan Township is moving forward with two significant infrastructure projects, with the Kankakee Bridge reconstruction now out for bid at an estimated cost of $1.6 million. Meanwhile, the Baker Road Bridge reconstruction project is more than halfway complete, according to a report from the Highway Commissioner.
Township Bridge Projects Key Points:
-
The Kankakee Bridge reconstruction project is now accepting bids, with the bid opening scheduled for July 16.
-
The estimated cost for the Kankakee Bridge project is $1.6 million.
-
Work on the Baker Road Bridge reconstruction is currently 55% complete.
Manhattan Township is advancing two major bridge reconstruction projects, with one heading to bid for $1.6 million and another already past the halfway point of construction, the township board learned on Tuesday, July 8, 2025.
In his monthly report, Highway Commissioner Jim Baltas announced that the Kankakee Bridge reconstruction project is now officially out for bid. The bid opening is scheduled for July 16, with the project carrying an estimated price tag of $1.6 million. This marks a critical step in moving the long-planned infrastructure upgrade toward the construction phase.
Baltas also provided a positive update on the Baker Road Bridge project, reporting that the reconstruction is now 55% complete. The project has been underway for several months and is progressing on schedule, aiming to restore a key local transportation link for residents. Both projects represent a significant investment in maintaining and improving the township’s rural road and bridge network.
Latest News Stories
Manhattan Board Approves Kubota RTV Purchase for Sidewalk Plowing
Hegseth promises to fix barracks, but work could take time
‘Long overdue’: Praise for HHS’ action to bar taxpayer-funded sex-change procedures
Gas prices drop, but taxes make Illinois pricier than Midwest neighbors
Liquor License Amendments Approved for Frankfort, Joliet, and Lockport Businesses
Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 16, 2025
Joliet Property Owner Cleared to Convert Non-Conforming Building into Two-Unit Residence
Colorado adopts first-of-its-kind water protections in U.S.
Epstein files redactions frustrate lawmakers
Supreme Court weighs gun owners’ challenge to IL transit carry ban
Nine pharmaceutical companies agree to most-favored-nation pricing
Congress leaves for holidays after zero progress on federal funding