Kankakee Bridge Project Out for Bid at $1.6 Million, Baker Road Bridge Nears Completion
Manhattan Township Meeting | July 2025
Article Summary: Manhattan Township is moving forward with two significant infrastructure projects, with the Kankakee Bridge reconstruction now out for bid at an estimated cost of $1.6 million. Meanwhile, the Baker Road Bridge reconstruction project is more than halfway complete, according to a report from the Highway Commissioner.
Township Bridge Projects Key Points:
-
The Kankakee Bridge reconstruction project is now accepting bids, with the bid opening scheduled for July 16.
-
The estimated cost for the Kankakee Bridge project is $1.6 million.
-
Work on the Baker Road Bridge reconstruction is currently 55% complete.
Manhattan Township is advancing two major bridge reconstruction projects, with one heading to bid for $1.6 million and another already past the halfway point of construction, the township board learned on Tuesday, July 8, 2025.
In his monthly report, Highway Commissioner Jim Baltas announced that the Kankakee Bridge reconstruction project is now officially out for bid. The bid opening is scheduled for July 16, with the project carrying an estimated price tag of $1.6 million. This marks a critical step in moving the long-planned infrastructure upgrade toward the construction phase.
Baltas also provided a positive update on the Baker Road Bridge project, reporting that the reconstruction is now 55% complete. The project has been underway for several months and is progressing on schedule, aiming to restore a key local transportation link for residents. Both projects represent a significant investment in maintaining and improving the township’s rural road and bridge network.
Latest News Stories
Op-Ed: Senate Bill 3070 provides sensible solution for students, manufacturers
Novotny, Slazyk Headline Lincoln-Way West’s Multi-Win Effort at Lockport Triangular
Illinois millionaire’s tax moves closer to November ballot
Oldest preserve expansion pushes acreage past 24,000 milestone
Lincoln-Way West Holds Off Lockport 3-2 in Tense Conference Clash
Lincoln-Way West Maximizes Opportunities to Walk Off Homewood-Flossmoor 4-3
Distance Runners, Throwers Propel Lincoln-Way West to Second-Place Finish at BBCHS Triangular
Meeting Summary and Briefs: Manhattan Park Board for March 12, 2026
Early Offensive Surge Propels Lincoln-Way West Past Oswego 11-4
Lusciatti’s Sprint Sweep, Spee’s 800 Crown Propel Lincoln-Way West to Second Place at Bud Mohns Invitational
Meeting Summary and Briefs: Will County Board Executive Committee for April 9, 2026
On the road to 100 years: How the Forest Preserve District expanded