Manhattan Eyes Major Water and Sewer Rate Hikes to Fund Over $50 Million in Infrastructure Projects

Spread the love

Article Summary: To address aging infrastructure and prepare for significant future growth, Manhattan officials are planning more than $50 million in crucial water and sewer system upgrades, which will necessitate a series of rate increases for residents over the next several years.

Manhattan Village Board Finance Workshop Key Points:

  • Future projects include a new $6 million water tower and a $42.6 million expansion of the wastewater treatment plant.

  • A proposed multi-year rate increase would begin with a $1.65 hike in the water usage rate on Jan. 1, 2026, followed by further increases in subsequent years.

  • Officials state the upgrades are necessary to replace 20-year-old equipment, accommodate a projected population of 20,000 by 2050, and meet stricter IEPA regulations.

MANHATTAN – Village officials are preparing for a massive, multi-year overhaul of Manhattan’s water and sewer infrastructure, a plan carrying a price tag of more than $50 million that will require gradual rate increases for residents to fund.

The scope of the necessary projects was detailed during a Village Board Finance Workshop on September 9. Mayor Mike Adrieansen said the workshop’s purpose was to review major improvements required within the next five years to ensure the village’s infrastructure remains reliable.

“After careful analysis with the Public Works Department and Finance Department, it’s necessary to increase water and sewer rates and certain fees,” Mayor Adrieansen said, proposing that the rate hikes be spread over three years to lessen the impact on residents.

The proposed projects include a new Public Works facility (

6million),anewwatertowerforWell7(

6 million), and a comprehensive expansion of the well water treatment plant estimated to cost $42.6 million. These are in addition to the ongoing $9.7 million project for the Well 7 treatment and radium removal facility.

Dan Small of Strand Associates, the village’s engineering consultant, explained that growth is a major driver for the upgrades. The village’s 2025 Comprehensive Plan projects a population of 20,000 by the year 2050, which will require the wastewater treatment plant’s capacity to double from its current 1.35 million gallons per day (MGD) to 2.7 MGD.

However, Small noted that growth is not the only factor. “The last project was in 2005 and the mechanicals are going to need to be replaced soon,” he said. “The mechanicals are about twenty years old and that is about the shelf life before items start breaking down.”

The expansion will also address new regulatory requirements from the Illinois Environmental Protection Agency (IEPA), which is reducing the allowable limit for phosphorus in treated wastewater.

To fund the bonds for these large-scale projects, the village is proposing a multi-step increase in utility rates. The plan includes a $1.65 increase in the water usage rate starting January 1, 2026, followed by annual increases of $0.61 for the next three years. The sewer rate would see a proposed increase of $1.31 each year, beginning in 2027 for three years. Officials noted these figures could be adjusted if grant funding is secured.

Leave a Comment





Latest News Stories

Will County Board Graphic.03

Meeting Summary and Briefs: Will County Board for February 19, 2026

Will County Board Meeting | February 19, 2026 Meeting SummaryThe Will County Board meeting on Thursday, February 19, 2026, was marked by significant zoning decisions, including the unanimous rejection of...
Will County Board Graphic.04

Board Approves Joliet Township Clean Fill Facility Despite Environmental Objections

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a map amendment and special use permit for a Clean Construction and Demolition Debris (CCDD) facility...
solar panels photovoltaics in solar farm

Will County Board Unanimously Rejects Controversial Solar Farm in Troy Township

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board unanimously rejected a special use permit for a commercial solar energy facility near Shorewood following strong opposition...
Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Will County Landfill Committee Meeting | February 10, 2026 Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to...
Meeting Briefs

Meeting Summary and Briefs: Lincoln-Way District 210 Board of Education for February 19, 2026

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 NEW LENOX – The Lincoln-Way Community High School District 210 Board of Education met on Thursday, February 19, 2026, to...
Will County Board Graphic.04

County Approves $1.9 Million for Wilmington-Peotone Road Engineering

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board authorized nearly $2 million in Motor Fuel Tax funds to begin Phase I design engineering for improvements...
Police Crime

County Board Authorizes Audit of Homer Glen Policing Contract; Officials Seek ‘True Cost’ of Services

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board unanimously approved a $75,000 contract to audit the cost of law enforcement services provided to the Village...
solar panels photovoltaics in solar farm

Soltage Drops Battery Storage Plans, Secures Extensions for Two Crete Solar Projects

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board granted second extensions to special use permits for two solar energy projects in Crete Township. The developer,...
Will County Board Graphic.02

Scrap Metal Drop-Off Near Mokena Approved by Single Vote

Will County Board Meeting | February 19, 2026 Article Summary: A contested proposal for an outdoor recyclable material drop-off facility in Frankfort Township passed by a single vote following objections from...
Will County Board Graphic.01

Landscape Business Approved on Cedar Road Despite ‘Dangerous Curve’ Concerns

Will County Board Meeting | February 19, 2026 Article Summary: The Will County Board approved a special use permit for a landscape business on Cedar Road in Homer Glen, despite concerns...
Committee-Ad-Hoc.Graphic

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for February 10, 2026

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Meeting SummaryThe Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, February 10, 2026, to continue its comprehensive...
Committee-Land Use.Graphic

Meeting Summary and Briefs: Will County Land Use & Development Committee for February 5, 2026

Will County Land Use & Development Committee Meeting | February 5, 2026 The Will County Land Use and Development Committee met on Thursday, February 5, 2026, to deliberate on several...
Screenshot 2026-03-22 at 12.12.19 PM

Meeting Summary and Briefs: Manhattan School District 114 for February 11, 2026

Manhattan School District 114 Meeting | February 11, 2026 The Manhattan School District 114 Board of Education held its regular meeting on Wednesday, February 11, 2026, at 6:30 p.m. at...
Screenshot 2026-02-22 at 5.06.42 PM

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for February 18, 2026

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Meeting SummaryThe Joliet Junior College Board of Trustees met on Wednesday, February 18, 2026, for a regular meeting dominated...
Committee-Executive.Graphic

Meeting Summary and Briefs: Will County Executive Committee for February 11, 2026

Will County Executive Committee Meeting | February 11, 2026 Meeting SummaryThe Will County Board Executive Committee met on Wednesday, February 11, 2026, tackling a heavy agenda focused on economic development...