“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension
Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited “ongoing uncertainty regarding federal renewable energy policy” as a cause for delay. The extension for the Pralle Farms Partnership project on West Kennedy Road pushes its deadline to February 2026.
Peotone Solar Farm Extension Key Points:
-
Project: A commercial solar farm by Pralle Farms Partnership on West Kennedy Road in Peotone Township.
-
Action: The board approved a second 180-day extension for the project’s special use permit, now valid until February 8, 2026.
-
Reason: The developer cited delays related to new federal renewable energy legislation, referred to as the “One Big Beautiful Bill.”
-
Vote: The extension was approved 19-1, with board member Katie Deane-Schlottman voting against the measure.
JOLIET — Citing “ongoing uncertainty regarding federal renewable energy policy,” developers of a commercial solar farm in Peotone Township were granted a second extension on their special use permit by the Will County Board on Thursday.
The project, located on a vacant property on West Kennedy Road and owned by Pralle Farms Partnership, was initially approved on March 16, 2023. Developer Trajectory Energy Partners received its first extension in February 2025.
In a memo to the board’s Land Use and Development Committee, Marguerite Kenny, a county Zoning Administrator, noted that the applicant submitted the second extension request on August 6, 2025. The request “provided a detailed letter further explaining the current federal regulation climate” following the passage of new legislation in July referred to as the “One Big Beautiful Bill.”
A building permit for the solar facility was created on March 7, 2025, but the application is still under review and awaiting required submittals, according to the memo. Special use permits typically expire after two years if construction is not lawfully established.
The board approved the second 180-day extension in a 19-1 vote, with Katie Deane-Schlottman casting the lone dissenting vote. The permit is now valid through February 8, 2026, giving the developers more time to navigate the federal policy landscape and finalize their construction permit.
Latest News Stories
Lincoln-Way West Claims WJOL Tournament Championship with 11-1 Win Over Lockport
Will County Kicks Off Comprehensive Land Resource Management Plan Update with Focus on Proactive Zoning and Environmental Justice
Infighting and Calls for Resignation Disrupt Will County Board Meeting
Lincoln-Way West Outlasts Marysville 6-5 in Eight-Inning Thriller
Lincoln-Way 210 Awards $1.98 Million Contract for Network Cabling Upgrades
Will County Land Use Committee Splits Votes on Massive Earthrise Solar Projects Amid Intense Public Opposition
Report: Coordinated resilience infrastructure is needed in age of AI
Will County P&Z Recommends Denial of 6,000-Acre “Pride of the Prairie” Solar Project After Contentious Hearing
U.S., NATO alliance on the line as Trump set to meet with Rutte
BREAKING: Trump fires Bondi, Blanche to lead DOJ
States sue Trump administration over rollback of some air pollution regulations
Energy affordability report ranks Illinois 31st, warns of ‘burdensome’ mandates