Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Manhattan Weather Full forecast →
Today Jun 4
Showers And Thunderstorms
79° 69°

Showers And Thunderstorms

💨 10 to 20 mph 💧 81%

Leave a Comment





Latest News Stories

Screenshot 2025-10-10 at 11.52.52 AM

Will County Board Backs Effort to Rename ‘Stigmatizing’ Chicago Sanitary and Ship Canal

Will County Executive Committee Meeting October 9, 2025 Article Summary: The Will County Board has thrown its support behind a regional effort to rename the Chicago Sanitary and Ship Canal,...
Screenshot 2025-10-10 at 12.12.04 PM

Access Will County Dial-a-Ride on Track for Full County-Wide Service in 2026

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Access Will County dial-a-ride program is set for a major expansion in 2026, with plans to...
WCO 2025-09-27 at 9.04.36 AM

Divided Will County Board Authorizes Condemnation for 143rd Street Widening

Article Summary: Following intense debate and emotional public testimony, the Will County Board narrowly approved a resolution to begin condemnation proceedings for the controversial widening of 143rd Street in Homer...
Screenshot 2025-10-10 at 11.39.44 AM

Will County Committee Approves Preliminary $161.6M Tax Levy on Split Vote Amid Heated Debate Over Spending

Will County Finance Committee Meeting October 7, 2025 Article Summary: The Will County Finance Committee on Tuesday narrowly approved a preliminary $161.6 million property tax levy for 2025, which projects...
Screenshot 2025-10-10 at 11.36.42 AM

Will County Eyes Major Overhaul to Consolidate Scattered Government Offices

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: Will County officials are formally debating a new facilities master plan to address aging buildings and dozens...
Screenshot 2025-10-10 at 11.20.27 AM

Sheriff’s Office Reports Crime Down 10%, Cites Body Cam Footage as Main Challenge of Safety Act

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Sheriff's Office reported a nearly 10% overall drop in crime compared to the same...
Screenshot 2025-10-10 at 11.52.24 AM

Will County Considers Moving Land Use Public Hearings Away from Full Board Meetings

Will County Executive Committee Meeting October 9, 2025 Article Summary: A proposal to move the final public hearing for zoning and land use cases from the full Will County Board...
Meeting Briefs

Meeting Summary and Briefs: Jackson Township Board for August 13, 2025

The Jackson Township Board took the next step in reviewing a proposed anaerobic digester project at its meeting on Wednesday, August 13, 2025, referring the plan from Elwood81, LLC, to...
Jackson Township

Jackson Township to Investigate Decade-Old High-Speed Rail Plan Through Elwood

Article Summary: Jackson Township officials are seeking information on a high-speed rail plan dating back to 2012 that would route a passenger line through the Elwood area. Supervisor Matt Robbins...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Park Board for August 14, 2025

The Manhattan Park Board made significant progress on its flagship Round Barn Farm project during its meeting on August 14, 2025. Commissioners unanimously approved hiring a new architect, Arete Design...
WCO 2025-09-27 at 9.04.36 AM

Meeting Summary and Briefs: Will County Board for September 18, 2025

The Will County Board navigated a contentious meeting on September 18, 2025, marked by narrow votes on two highly debated land use issues in Crete and Homer Glen. The board...
jackson township graphic.1

Jackson Township Approves Settlement with Joliet, Union Pacific Over ICC Case

Article Summary: The Jackson Township Board unanimously approved a settlement agreement involving the City of Joliet and Union Pacific Railroad, formally resolving a multi-year case before the Illinois Commerce Commission....
Meeting Briefs

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 Board of Education for September 18, 2025

The Lincoln-Way Community High School District 210 Board of Education on Thursday, September 18, 2025, formally adopted a $172.7 million budget for the 2025-2026 school year. The budget includes a...
manhattan park district graphic.1

Manhattan Park Board Deadlocks on Paying for Sports Complex Plan, Motion Fails

Article Summary: A proposal for the Manhattan Park District to fund an architectural concept plan for a new sports complex failed to pass on Thursday, August 14, 2025, after a...
manhattan elwood library graphic.5

Manhattan-Elwood Library Board Adopts Annual Budget and Appropriation Ordinance

Article Summary: The Manhattan-Elwood Public Library District Board of Trustees has formally adopted its budget for the upcoming fiscal year following a public hearing. The approval of the combined Budget...