Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Spread the love

Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Leave a Comment





Latest News Stories

Meeting Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
Meeting Briefs

Manhattan Village Board Briefs

2025 Road Resurfacing Approved: The board approved an IDOT resolution for maintenance under Illinois code for the village's 2025 resurfacing project totaling $750,000. The project will complete streets that were...
About Us Website Header - 1

New Lenox Library Board Seats New Trustees, Reorganizes After Election

NEW LENOX – The New Lenox Public Library District Board of Trustees officially seated its newly elected members and reorganized its leadership and committee assignments for the new term at...
New-Lenox-School-122.3

New Lenox D122 Board Approves Nearly $300,000 for Summer Maintenance Projects

The New Lenox School District 122 Board of Education has approved a comprehensive list of 56 maintenance and capital improvement projects to be completed over the summer, allocating a total...
new-lenox-fire-district-stations.3

New Lenox Fire District to Launch Comfort Dog Program for First Responders, Community

NEW LENOX – The New Lenox Fire Protection District is adding a four-legged member to its team after the Board of Trustees unanimously approved the creation of a new comfort...
new-lenox-library.2-1

Library’s ‘Studio’ Draws Record Crowds with New Tech and Creative Programs

NEW LENOX – The New Lenox Public Library’s creative hub, The Studio, is experiencing a surge in popularity, shattering attendance records and successfully launching new technology-driven programs, according to a...
New-Lenox-School-122.5

D122 to Spend $24,950 on Professional Enrollment Forecast

New Lenox School District 122 will hire an outside firm to conduct a comprehensive, 10-year enrollment forecast at an estimated cost of $24,950. The Board of Education approved an agreement...
Police blue and red flashing light on the car in the street

Manhattan Police Report

Disclaimer: Charges against each defendant are merely an accusation, with all defendants presumed innocent unless proven guilty in a court of law. On June 25th, officers stopped Jr. Vrabel, Daniel (44) of Joliet, Illinois...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
Screenshot 2025-07-06 at 9.50.39 AM

Lincoln Way District 210 Approves $2.1 Million Budget Amendment, Maintains Strong Financial Position

Lincoln Way Community High School District 210 board members unanimously approved an amended fiscal year 2025 budget Thursday night that increases the district's operating surplus to $2.1 million while maintaining...
Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Screenshot 2025-07-06 at 9.45.35 AM

District 210 Approves Administrative Restructuring, Staff Salary Increases

Lincoln Way Community High School District 210 board members approved administrative restructuring and salary increases for non-union clerical support staff during closed session actions Thursday night. The board unanimously approved...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...
Joliet-Junior-college.-Graphic-Logo.3

Students, Trustees Emphasize Importance of Inclusivity and Flag Raisings at JJC

From a recent graduate’s public plea to trustee remarks on federal policies, the theme of student belonging and inclusivity was a prominent thread at the Joliet Junior College Board of...