Screenshot 2025-10-10 at 11.39.50 AM

Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Spread the love

Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Manhattan Weather Full forecast →
Today Jun 6
Showers And Thunderstorms Likely
83° 70°

Showers And Thunderstorms Likely

💨 5 mph 💧 64%

Leave a Comment





Latest News Stories

Will County Board Graphic.03

Will County Approves Diamond Enterprise Zone Expansion to Support $355 Million Energy Investment

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Executive Committee unanimously approved ordinances expanding the Diamond Enterprise Zone to include the Village of Braceville. The...
will county Committee-Legislative.Graphic

Federal Update: DHS Shutdown, War Powers, and Housing Legislation Dominate Washington

Legislative Committee Meeting | March 3, 2026 Article Summary: Will County's federal lobbyists briefed the Legislative Committee on a turbulent week in Washington, D.C., highlighting the passage of a major bipartisan...
Will County Finance Logo

Will County Corporate Revenues Surpass Expectations, Igniting Debate Over Delinquent Tax Sales

Will County Finance Committee Meeting | March 3, 2026 Article Summary: A routine review of the county’s year-end corporate fund revealed that revenues exceeded budgeted expectations by millions, largely driven by...
Will County Public Works Committee

Meeting Summary and Briefs: Will County Public Works and Transportation Committee for March 3, 2026

Will County Public Works and Transportation Committee Meeting | March 3, 2026 The Will County Public Works and Transportation Committee met on Tuesday, March 3, advancing millions of dollars in...
solar panels photovoltaics in solar farm

Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized...
manhattan fire district graphic logo.1

Construction Progresses on New Manhattan Fire Station, August Completion Anticipated

Manhattan Fire Protection District Meeting | February 17, 2026 Article Summary: The Manhattan Fire Protection District's new fire station is advancing rapidly through its construction phases, with concrete work finished...
Will County Board Graphic.03

Will County Committee Postpones Liquor, Ad-Hoc Committee: Gaming, and Tobacco Ordinance Updates Amid Extensive Revisions

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: A Will County Board committee paused the advancement of major updates to the county's liquor, video...
solar panels photovoltaics in solar farm

Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: Reversing a deadlocked Planning and Zoning Commission, the Will County Land Use and Development Committee unanimously approved...
Will County Board Graphic.04

Will County Advances Nearly $1.5 Million in Right-of-Way and Improvement Agreements for Weber, Gougar, and Laraway Roads

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Public Works and Transportation Committee authorized a slate of professional services and construction agreements Tuesday to...
Will County Public Works Committee

Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to...
will county Committee-Legislative.Graphic

Will County Board Backs $10 Million State Public Health Grant Increase Amid Funding Cuts

Legislative Committee Meeting | March 2026 Article Summary: The Will County Legislative Committee unanimously approved a resolution supporting a state legislative push to increase the Local Health Protection Grant by $10...
Monee Fire

Barn Fire on Whispering Hills Lane Claims Livestock, Draws Extensive Mutual Aid Response

Article Summary: A massive late-night structure fire completely destroyed a 60-by-60-foot wood frame barn on Whispering Hills Lane, resulting in the loss of 15 animals but no human injuries. Firefighters from...
Will County Board Graphic.01

Will County Public Works Committee Shelves License Plate Reader Agreement Amid Bipartisan Privacy Concerns

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee abruptly removed an agreement with the Illinois State Police...
Will County P&Z Logo Planning Zoning.2

Will County Planning and Zoning Commission Overrides Staff to Approve New Lenox Accessory Building Variance

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission voted to override a staff recommendation of denial, approving a...
sheriff dog

Will County Sheriff’s Office Welcomes Remi, First Electronic Scent Detection Dog

Article Summary: The Will County Sheriff’s Office announced the addition of Remi, a Labrador serving as the department's first Electronic Scent Detection dog. The newly trained K9 will assist investigators...