Will County Public Works & Transportation Committee Meeting October 7, 2025

Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million contract to P.T. Ferro Construction Co. for the major reconstruction and widening of a segment of Bell Road. The project, spanning from 151st Street to Martingale Lane, is expected to begin in November 2025 and will include new sidewalks, storm sewers, and modernized traffic signals.

Bell Road Project Key Points:

  • P.T. Ferro Construction Co. was the low bidder for the project with a bid of $10,400,058.22.

  • The project involves roadway widening and reconstruction on Bell Road (County Highway 16) from 151st Street to Martingale Lane.

  • Work is scheduled to begin in November 2025 and is estimated to be completed by November 20, 2026.

  • The roadway will remain open during construction with periodic lane closures controlled by flaggers.

JOLIET, IL – A significant road improvement project is set to begin in the Homer Glen area next year after the Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a $10.4 million construction contract.

The committee unanimously confirmed the award to Joliet-based P.T. Ferro Construction Co., which submitted the lowest bid for the reconstruction and widening of Bell Road (County Highway 16) between 151st Street and Martingale Lane. The contract is for $10,400,058.22.

The project is a major undertaking aimed at improving traffic flow and safety along the busy corridor. According to a project summary from the Will County Division of Transportation, the scope of work includes roadway widening and reconstruction with new pavement, installation of sidewalks and storm sewers, and modernization of traffic signals. The project will also involve building a soldier pile retaining wall, new street lighting, and pavement markings.

Construction is slated to begin in November 2025, with an estimated completion date of November 20, 2026. Officials have stated that Bell Road will remain open to traffic throughout the construction period, though drivers should expect periodic lane closures controlled by flaggers.

The contract was awarded following a bid letting on September 17, 2025.

The resolution confirming the contract award will now go to the full Will County Board for final approval at its October 16 meeting. Funding for the improvements will come from a combination of sources, including Motor Fuel Tax, RTA Tax, and County Highway Tax funds.

Leave a Comment





Latest News Stories

Three years later, Inflation Reduction Act blamed for higher Medicare costs

Three years later, Inflation Reduction Act blamed for higher Medicare costs

By Tom JoyceThe Center Square This past weekend marked the third anniversary of the Inflation Reduction Act, signed into law by former President Joe Biden in 2022. While the law...
Illinois quick hits: Prosecutors charge two more in Tren de Aragua case; Senate Energy and Public Utilities Committee meets today; Illinois Little League team loses in World Series

Illinois quick hits: Prosecutors charge two more in Tren de Aragua case; Senate Energy and Public Utilities Committee meets today; Illinois Little League team loses in World Series

By Jim Talamonti | The Center SquareThe Center Square Prosecutors charge two more in Tren de Aragua case State prosecutors have charged two more migrants as part of an investigation...
Report: Human Rights Campaign pressures transgender procedures on minors

Report: Human Rights Campaign pressures transgender procedures on minors

By Tate MillerThe Center Square (By Tate Miller) – The Human Rights Campaign pressures children’s hospitals into performing transgender procedures on minors, according to a Do No Harm report. Do...
Manhattan Township

Kankakee Bridge Project Out for Bid at $1.6 Million, Baker Road Bridge Nears Completion

Manhattan Township Meeting | July 2025 Article Summary: Manhattan Township is moving forward with two significant infrastructure projects, with the Kankakee Bridge reconstruction now out for bid at an estimated cost...
Everyday Economics: Housing market and Fed policy in focus in the week ahead

Everyday Economics: Housing market and Fed policy in focus in the week ahead

By Orphe DivounguyThe Center Square This week brings crucial updates on America's housing market struggles and hints about where interest rates might head next. Housing Data Dump Several major housing...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Fire Protection District Board of Trustees for July 11, 2025

At a special meeting on July 11, the Manhattan Fire Protection District Board of Trustees took decisive action to advance its new fire station project. The board moved forward with...
Exec Cmte 8.14.25.3

Executive Committee Considers $12,000 Strategic Planning Initiative with University of St. Francis

Article Summary: The Will County Executive Committee is considering a proposal from the University of St. Francis to lead a six-month, $12,178 strategic planning process. The initiative is aimed at...
Businesses brace for new tax challenges amid global tariff focus

Businesses brace for new tax challenges amid global tariff focus

By Brett RowlandThe Center Square U.S. businesses and their partners across the globe are looking to make sure they comply with the highest import duties in decades amid a worldwide...
Illinois takes over health insurance marketplace in 2026 amid skepticism

Illinois takes over health insurance marketplace in 2026 amid skepticism

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Illinois will fully take over operation of its health insurance marketplace in 2026, moving away from...
WATCH: IL state reps challenge IEMA-OHS responses to local agencies

WATCH: IL state reps challenge IEMA-OHS responses to local agencies

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois Emergency Management Agency and Office of Homeland Security officials are promising to be more responsive to...
Judge expands restraining order against 'Beto' O’Rourke, adds ActBlue

Judge expands restraining order against ‘Beto’ O’Rourke, adds ActBlue

By Bethany BlankleyThe Center Square A judge has expanded a temporary restraining order against former U.S. Rep. Robert (Beto) O’Rourke and his organization, Powered by People, as well as ActBlue...
manhattan fire district graphic logo.3

District to Issue Up to $8.75M in Bonds for New Fire Station

Article Summary: The Manhattan Fire Protection District board approved an ordinance to issue up to $8.75 million in general obligation bonds to fund its new fire station. Officials said the...
Exec Cmte 8.14.25.2

Executive Committee Members Decry Roadside Litter, Call for Action Against Garbage Haulers

Article Summary: Will County Executive Committee members expressed frustration over what they described as a worsening problem of litter blowing from garbage trucks across the county. Members called for better...
Reversing Biden’s precedent, students complete FAFSA in minutes at beta-testing event

Reversing Biden’s precedent, students complete FAFSA in minutes at beta-testing event

By Tate MillerThe Center Square President Donald Trump’s Department of Education is working to restore the student aid FAFSA form after the Biden administration made what should be a couple-minute...
Trump, Zelenskyy to meet Monday in steps toward peace with Russia

Trump, Zelenskyy to meet Monday in steps toward peace with Russia

By Sarah Roderick-FitchThe Center Square Following a “successful” meeting in Alaska with Russian President Vladimir Putin, President Donald Trump said he is going straight for a “peace agreement” in a...