Will County Board Land Use Committee Graphic.4

Will County Committee Grants Extensions for Crete, Washington Township Solar Projects

Spread the love

Will County Land Use & Development Committee Meeting | November 6, 2025

Article Summary: The Will County Land Use and Development Committee granted 180-day extensions for two commercial solar energy projects in Crete and Washington Townships, giving the developer additional time to complete the necessary permitting before their initial approvals expire.

Solar Farm Permit Extensions Key Points:

  • A first extension was approved for a TPE Development affiliated project in Crete Township (ZC-23-108), pushing its deadline to June 19, 2026.

  • A first extension was also granted for a related TPE project in Washington Township (ZC-24-020), moving its deadline to November 12, 2026.

  • The extensions were requested to allow more time to complete complex permitting and pre-construction processes.

  • Special use permits for solar facilities in Will County typically expire after two years if construction has not legally commenced.

JOLIET, IL — Two large-scale solar energy projects in eastern Will County were granted more time to get off the ground after the Will County Land Use and Development Committee on Thursday, November 6, 2025, approved their first 180-day permit extensions.

The committee unanimously approved the requests for projects in Crete and Washington townships, both associated with TPE Development, LLC. The extensions are necessary because the special use permits approved by the County Board are set to expire within the next year, and the projects have not yet completed the building permit process to legally establish the use.

The first extension was for case SEXT-25-019, concerning a commercial solar facility at the southeast corner of South Nacke Road and West Loves Lane in Crete Township. Originally approved on December 21, 2023, the permit was set to expire in December 2025. The applicant has applied for a building permit but cited needing more time to complete the process. The extension is now valid through June 19, 2026.

The second approval was for case SEXT-25-020, for a solar facility at the southeast corner of West Indiana Avenue and South Western Avenue in Washington Township, near Beecher. This project was approved on May 16, 2024, and its permit was set to expire in May 2026. According to county staff, the applicant has not yet applied for a building permit. The extension pushes the new expiration date to November 12, 2026.

Under the Will County Zoning Ordinance, a special use permit lapses after two years if the use has not been legally established. The ordinance allows the County Board to grant up to four separate 180-day extensions for “good cause.” Jordan Belknap, representing the applicant, stated they have been working with local authorities, including University Park, on necessary road improvements for the Crete project before construction can begin.

Manhattan Weather Full forecast →
Today Jun 5
Mostly Sunny then Chance Showers And Thunderstorms
87° 67°

Mostly Sunny then Chance Showers And Thunderstorms

💨 5 to 10 mph 💧 30%

Leave a Comment





Latest News Stories

Will County Board Land Use Committee Graphic.4

Committee Postpones Vote on Brandon Road Fill Operation After Tree Clearing Allegations

Will County Land Use & Development Committee Meeting | December 2025 Article Summary: The Will County Land Use and Development Committee voted to postpone a decision on a proposed clean...
Meeting Briefs

Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 2, 2025

Will County Planning and Zoning Commission Meeting | December 2, 2025 Overall Meeting SummaryThe Will County Planning and Zoning Commission met on December 2, 2025, to consider a variety of...
Metra

Metra Announces No Fare Hikes; Highlights Bridge Projects in Joliet and Mokena

Will County Committee of the Whole Meeting | December 2025 Article Summary: Metra officials presented a balanced 2026 budget to the Will County Board, confirming that riders will not see...
Screenshot 2025-12-04 at 11.30.23 AM

Village Bolsters Winter Operations with New Hires and Truck Purchase

Village of Manhattan Board of Trustees Meeting | December 2, 2025 Article Summary: To prepare for the winter season, the Manhattan Village Board authorized the hiring of a seasonal snowplow...

Public Works Committee: Will County Consolidates Paratransit Services Amid Funding Debates

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: The Will County Board’s Public Works Committee advanced an agreement to consolidate paratransit services into a single countywide...
Will County P&Z Logo Planning Zoning

P&Z Commission: Peotone Area Variances Forwarded for Garage and Pole Barn

Will County Planning and Zoning Commission Meeting | December 2, 2025 Article Summary: The Will County Planning and Zoning Commission approved variance requests for two properties in Peotone Township, allowing...
Meeting Briefs

Meeting Summary and Briefs: Manhattan-Elwood Public Library District Board for October 2025

Manhattan-Elwood Public Library District Board Meeting | October 2025 The Manhattan-Elwood Public Library District Board met on Tuesday, October 27, 2025, to conduct a Tax Levy Hearing and its regular...

Peotone License Plate Camera Renewal Sparks Privacy Debate in Public Works Committee

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: A renewal of an agreement allowing license plate reading (LPR) cameras in Peotone passed the Public Works Committee,...
Screenshot 2025-12-04 at 11.30.16 AM

No Accidents Reported Since Route 52 Stop Sign Installation; Local Business Donates Cameras

Village of Manhattan Board of Trustees Meeting | December 2, 2025 Article Summary: Police Chief Jeff Gulli reported that safety measures at the intersection of Route 52 and North Street...
manhattan elwood library graphic.2

Library Board Authorizes Online Bill Pay and Formalizes Friends of the Library Agreement

Manhattan-Elwood Public Library District Board Meeting | October 2025 Article Summary: The Manhattan-Elwood Public Library District Board moved to modernize financial operations by approving online bill payment services and solidifying...
Screenshot 2025-12-05 at 12.00.30 PM

Joliet Unity Movement Criticizes Board’s Handling of Cannabis Tax Revenue

Will County Board Meeting | December 4, 2025 Article Summary: During public comment, the Joliet Unity Movement denounced a recent board vote that redirected cannabis tax revenue away from community...

Safety Upgrades Planned for Wilmington-Peotone Road; Gas Line Proposal Rejected

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: The Will County Public Works Committee approved a $1.9 million engineering contract for improvements to a dangerous stretch...
Screenshot 2025-12-04 at 11.30.01 AM

Manhattan Trustees Approve 2025 Property Tax Levy

Village of Manhattan Board of Trustees Meeting | December 2, 2025 Article Summary: The Manhattan Village Board approved a property tax levy of approximately $3.8 million for the upcoming fiscal...
Screenshot 2025-12-05 at 11.56.48 AM

Tensions Flare as Board Members Clash Over Budget Process and Protocol

Will County Board Meeting | December 4, 2025 Article Summary: A special meeting intended to fix a budget error turned contentious as board members traded accusations regarding transparency, meeting conduct,...
Screenshot 2025-12-05 at 11.57.25 AM

Will County Board Approves $2.7 Million Reserve Draw to Finalize 0% Tax Levy

Will County Board Meeting | December 4, 2025 Article Summary: The Will County Board unanimously voted to transfer approximately $2.78 million from cash reserves to balance the fiscal year 2026...