Consensus for power supply solution still elusive

Consensus for power supply solution still elusive

Spread the love

(The Center Square) – Rapid expansion of data centers in the mid-Atlantic region has leaves its power grid’s operator, PJM, standing at a crossroads: how can electricity supply keep up with exponential growth in demand without spiking bills for ratepayers?

After a Wednesday meeting with all of the organizations members – which include utility companies, state regulators, power plants, transmission providers, project developers, and commercial and industrial businesses – there’s still no path forward.

This, despite 12 proposals put forward for a vote. None earned majority support.

“The growth of data centers is colliding with the reality of the power grid,” said Tom Rutigliano, senior advocate for climate and energy at Natural Resources Defense Council. The advocacy group worked with Sen. Katy Fry Hester, D-Md., on one of the rejected plans.

Rutigliano told The Center Square that data centers are showing up and quickly adding cities’ worth of electric demand to the grid. Figuring out how to build power plants quickly enough to meet that demand is a $100 billion question, and reliability is at stake.

He surmises that PJM members ultimately backed proposals that served their own interests, preventing any real solution from advancing and leaving the grid’s board of directors with a hard choice – one he is optimistic will incorporate the best of each plan.

“We hope they fulfill their obligation to the 67 million people in the PJM region and commit to protecting reliability, treat all customers fairly, and not subsidize data centers at public expense,” Rutigliano said.

In addition to grappling with the core issues of reliability and affordability, open access is just as critical, Rutigliano said. It ensures all generators, including clean energy projects, have an equal opportunity to connect to the grid.

He warned that some proposed fast-track processes would heavily favor large fossil fuel plants, creating a permanent two-tier system where fossil fuel “gets a kind of concierge class connect to the grid and clean energy sits in coach.” From where NRDC sits, he added, that would be an unacceptable outcome.

Rutiglio acknowledged that while renewables alone aren’t enough to guarantee grid reliability, strategically combining them with storage and maintaining a diverse energy mix can create a reliable grid.

It is absolutely feasible, he said, to achieve 80-95% renewable integration. And, though the last stretch is the most difficult, it’s nowhere near being a problem – renewables make up single-digit percentages on PJM’s grid.

He said that renewables, combined with energy storage, can be built far faster than new gas turbines; often in 18 to 24 months, compared to years-long turbine waitlists and pipeline delays. Because storage is quicker to deploy and easier to site, he hopes the final policy outcome will encourage tech companies toward large-scale storage solutions. The goal, he added, isn’t to block data centers but to ensure they don’t shift risks onto the public, which is the goal of the “bring your own” proposals.

Roughly one-third of a data center’s cost is the power plant needed to serve it, he stated, and under the current system, taxpayers foot the bill for speculative projects – whether they get built or not – which he suggests is one of the main drivers for “bring your own.”

The voting at the Nov. 19 meeting resulted in none of the 12 proposal packages obtaining a requisite “passing” vote, Jeffrey Shields, PJM spokesman, told The Center Square via email.

“PJM opened this conversation about the integration of large loads and greatly appreciates our stakeholders for their contributions to this effort,” he said. ”The stakeholder process produced many thoughtful proposals, some of which were introduced late in the process and require additional development.”

This vote, Shields said, is advisory to PJM’s independent board, which can and does expect to act on large load additions to the system and will make its decision known in the next few weeks.

Leave a Comment





Latest News Stories

Will County Finance Logo

Consultant Updates Finance Committee on Homer Glen Police Cost Study

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: A consultant hired to evaluate the financial implications of the Village of Homer Glen launching its own...
Lincoln Way West Track

Lincoln-Way West Girls Display Middle-Distance Strength at Central Invitational

The Lincoln-Way West girls’ track and field team battled through a deep and competitive field on Saturday, April 11, at the Lincoln-Way Central Girls Invitational. Competing against some of the...
Lincoln Way West Track

Lincoln-Way West Secures Eight Individual Victories, Takes Third in Varsity A at Best 4 Invitational

The Lincoln-Way West boys' track and field team showcased its elite top-end talent on Saturday, April 11, bringing home eight individual flight championships at the highly competitive Best 4 Invitational...
Lincoln Way West Warriors Softball

Oswego Outlasts Lincoln-Way West 5-3 in Nine-Inning Thriller

The Oswego varsity softball team relied on timely late-game heroics and a clutch relief pitching performance from Jaelynn Anthony to secure a hard-fought 5-3 victory over host Lincoln-Way West in...
Screenshot 2026-04-08 at 3.23.31 PM

Manhattan Renews Will County LPR Camera Agreement as Police Chief Highlights Crime-Solving Successes

Village of Manhattan Board of Trustees Meeting | April 7, 2026 Article Summary: The Village Board approved the renewal of an intergovernmental agreement to maintain two license plate reading cameras...
Screenshot 2026-04-10 at 1.52.27 PM

Manhattan 114 Board Advances Facility Upgrades and Reviews Transportation Bids

Manhattan School District 114 Board of Education Meeting | April 8, 2026 Article Summary: The Manhattan School District 114 Board of Education approved an independent contractor agreement for exterior upgrades...
Untitled design - 1

Fish fight: action-packed eagle pic wins March photo contest

Laurie Lasseter of Woodridge snapped a photo of an eagle and herring gull locked in battle recently, and the shot was picked as the March winner in the District's Preserve...
Police Crime

Illinois State Police Investigating Fatal Officer-Involved Shooting in Bradley

Article Summary: The Illinois State Police is investigating a fatal officer-involved shooting that occurred after Bradley Police officers encountered an armed man during a mid-day well-being check. Bradley Officer-Involved Shooting...
Monee Car Fire

Fire Department Responds to Monee Car Fire

Monee firefighters responded to a car fire on Manhattan-Monee Road April 10th. No injuries were reported.
NL Fire

New Lenox Firefighters Extinguish Garage Fire, Rescue Pets on Somerset Court

Article Summary: The New Lenox Fire Protection District quickly contained a Friday morning garage fire on Somerset Court, preventing the blaze from spreading to the home's main living area and...
WCO-Capital Improvements & IT Apr 07 214

Will County Explores Multi-Million Dollar Downtown Joliet Consolidation and City Partnership

Will County Capital Improvements & IT Committee Meeting | April 7, 2026 Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county...
will county board meeting.6

Will County Partners with LNS Development for Laraway Road Drainage Improvements in New Lenox

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: The county approved a cost-sharing agreement with a private developer to build shared stormwater management facilities...
Will County Board Graphic.03

Will County Hires LEAP HR Consulting for $12,000 Strategic Plan

Will County Board Meeting | March 19, 2026 Article Summary: Seeking to unify its vision and improve onboarding for new members, the Will County Board will launch a four-month strategic...
Will County Finance Logo

Will County Finalizes 2025 Tax Levy at $159.5 Million, Limiting Rate Drops

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 Article Summary: The Will County Finance Committee reviewed the final 2025 tax levy extension numbers, which came in slightly...
Will County Board Graphic.02

Will County to Take Jurisdiction of Countyline Road Following $1.8 Million Agreement with Kankakee County

Will County Public Works & Transportation Committee Meeting | April 7, 2026 Article Summary: Will County will absorb a 4.27-mile stretch of Countyline Road into its highway system, aided by...