solar panels photovoltaics in solar farm

New Lenox to Host Large Pollinator-Friendly Solar Farm

Spread the love

Will County Board Meeting | November 2025

Article Summary: The Will County Board unanimously approved a special use permit for a commercial solar energy facility spanning approximately 63 acres in New Lenox Township. The project, located on South Spencer Road, will feature over 12,000 solar panels and includes plans for native pollinator vegetation.

Spencer Road Solar Key Points:

  • Location: A 110-acre parcel on South Spencer Road, south of 1100 S. Spencer Road, New Lenox. The solar facility will occupy ~63 acres.

  • Scale: Two facilities (2.4 MW and 2.85 MW) comprising 12,029 solar panels on single-axis trackers.

  • Pollinator Focus: The board granted variances for plant height (up to 36 inches) and mowing frequency (once per year) to allow for deep-rooted native pollinator plants.

  • Community Impact: The Village of New Lenox did not object to the project, subject to screening conditions which were included in the approval.

NEW LENOX – A significant new solar energy development is coming to New Lenox Township following a unanimous 22-0 vote by the Will County Board on Thursday.

The project, developed by Nexamp Solar under the names “Spencer Road Solar East” and “Spencer Road Solar West,” will transform agricultural land into a solar farm capable of generating over 5 megawatts of power.

A key feature of this development is its designation as a “pollinator-friendly” site. To support this, the Board approved two specific variances: allowing ground cover plants to grow up to 36 inches (ordinance limit is 13 inches) and reducing the required mowing frequency to once per year.

“Native pollinators are typically plants that have deep root systems that recharge the agricultural soils… and are natural weed prevention,” County Land Use staff noted in their report.

While three objectors raised concerns about wildlife disruption and aesthetics during the public hearing process, the project received a letter of non-objection from the Village of New Lenox, provided that landscape screening is installed along the western fence line. The project will also feature an 8-foot “fixed knot” farm fence rather than chain link, a requirement intended to be more wildlife-friendly.

The Forest Preserve District of Will County also weighed in, encouraging the developer to select native species that support the local ecosystem. The project is expected to bring 20 to 25 construction jobs to the area.

Leave a Comment





Latest News Stories

Meeting Briefs

In Brief: Capital & IT News

Here are other highlights from the Will County Capital Improvements & IT Committee meeting on Tuesday. Successful Fire Drill at County BuildingThe Will County Office Building held its first full...
Meeting Briefs

Will County Finance Committee July 1 Meeting Briefs

Bond Refinancing Advances: Finance Committee approved an ordinance authorizing up to $200.8 million in bond refinancing that could save taxpayers more than $716,000. The measure moves to the full County...
Meeting Briefs

Will County Public Works Committee Juliy 1 Meeting Briefs

ROAD CONTRACTS APPROVED Austin Tyler Construction Contract: The committee approved a $691,544 contract with Austin Tyler Construction for resurfacing River Road from East Frontage Road to Prairie Creek Bridge and...
Meeting Briefs

Manhattan Village Board Briefs

2025 Road Resurfacing Approved: The board approved an IDOT resolution for maintenance under Illinois code for the village's 2025 resurfacing project totaling $750,000. The project will complete streets that were...
About Us Website Header - 1

New Lenox Library Board Seats New Trustees, Reorganizes After Election

NEW LENOX – The New Lenox Public Library District Board of Trustees officially seated its newly elected members and reorganized its leadership and committee assignments for the new term at...
New-Lenox-School-122.3

New Lenox D122 Board Approves Nearly $300,000 for Summer Maintenance Projects

The New Lenox School District 122 Board of Education has approved a comprehensive list of 56 maintenance and capital improvement projects to be completed over the summer, allocating a total...
new-lenox-fire-district-stations.3

New Lenox Fire District to Launch Comfort Dog Program for First Responders, Community

NEW LENOX – The New Lenox Fire Protection District is adding a four-legged member to its team after the Board of Trustees unanimously approved the creation of a new comfort...
new-lenox-library.2-1

Library’s ‘Studio’ Draws Record Crowds with New Tech and Creative Programs

NEW LENOX – The New Lenox Public Library’s creative hub, The Studio, is experiencing a surge in popularity, shattering attendance records and successfully launching new technology-driven programs, according to a...
New-Lenox-School-122.5

D122 to Spend $24,950 on Professional Enrollment Forecast

New Lenox School District 122 will hire an outside firm to conduct a comprehensive, 10-year enrollment forecast at an estimated cost of $24,950. The Board of Education approved an agreement...
Police blue and red flashing light on the car in the street

Manhattan Police Report

Disclaimer: Charges against each defendant are merely an accusation, with all defendants presumed innocent unless proven guilty in a court of law. On June 25th, officers stopped Jr. Vrabel, Daniel (44) of Joliet, Illinois...
JJC-Graphic-Logo

JJC Trustees Approve Contentious FY26 Budget After Heated Debate, Failed Postponement

The Joliet Junior College Board of Trustees on Wednesday approved a $322.3 million budget for fiscal year 2026, but not before a tense debate that saw a motion to postpone...
Screenshot 2025-07-06 at 9.50.39 AM

Lincoln Way District 210 Approves $2.1 Million Budget Amendment, Maintains Strong Financial Position

Lincoln Way Community High School District 210 board members unanimously approved an amended fiscal year 2025 budget Thursday night that increases the district's operating surplus to $2.1 million while maintaining...
Joliet-Junior-college.-Graphic-Logo.5

JJC’s ‘12x12x12’ Initiative Boosts College Credits, Increases Matriculation Rate

Joliet Junior College’s ambitious "12x12x12" initiative is yielding significant results, leading to more high school students earning college credits and a greater percentage of them choosing to attend JJC after...
Screenshot 2025-07-06 at 9.45.35 AM

District 210 Approves Administrative Restructuring, Staff Salary Increases

Lincoln Way Community High School District 210 board members approved administrative restructuring and salary increases for non-union clerical support staff during closed session actions Thursday night. The board unanimously approved...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Meeting Highlights Tensions Over Legal Bills, Trustee Conduct

An otherwise routine vote to approve monthly bill payments ignited a tense exchange at the Joliet Junior College Board of Trustees meeting Wednesday, revealing ongoing friction over redacted legal invoices,...