Land Use Committee: Monee Solar Projects Granted Extensions; Battery Storage Plans Dropped
Will County Land Use & Development Committee Meeting | December 2025
Article Summary: The Will County Land Use and Development Committee granted time extensions for two separate solar farm projects in Monee Township. During the review, it was revealed that the developer has removed the battery energy storage systems (BESS) from both applications, and Board Member Judy Ogalla clarified her stance on the projects based on their proximity to residential areas.
Monee Solar Extensions Key Points:
-
Project 1 (Monee Solar): Located at 26845 S. Will Center Road; extension approved 5-1.
-
Project 2 (Monee Solar West): Located at West Pauling Road and South Will Center Road; extension approved 6-0.
-
Major Change: The developer is no longer pursuing Battery Energy Storage Systems (BESS) at either location; the permits for those specific components will lapse.
-
New Deadline: Special use permits for the solar arrays are now valid through July 17, 2026.
The Will County Land Use and Development Committee on Thursday, Dec. 4, 2025, approved “first extensions” for two separate commercial solar energy facilities in Monee Township, giving the developers until July 2026 to obtain building permits.
The first project, Monee Solar, LLC, located at 26845 S. Will Center Road, was originally approved in January 2024. Staff reported that while the original approval included a special use permit for a Battery Energy Storage System (BESS), the applicant has decided not to move forward with the battery component. The extension request applies only to the solar farm itself.
Board Member Judy Ogalla voted against the extension for this specific site.
“I would not have supported this,” Ogalla said, referring to the original vote in early 2024. “That is way too close to residential… I would be a no on that.”
The committee voted 5-1 to approve the extension, with Ogalla voting no.
The second project, Monee Solar West, LLC, located at the northwest corner of West Pauling Road and South Will Center Road, also received an extension. Similar to the first project, the developer has dropped plans for a battery storage system at this site.
Ogalla voted in favor of this second extension, distinguishing it from the first project based on its location.
“The second one is not near residential, so I would be supporting that,” Ogalla noted.
The committee voted 6-0 to approve the extension for Monee Solar West. Both special use permits are now valid through July 17, 2026.
Latest News Stories
Manhattan Township Donates $3,000 to Will County Community Concerns
New Lenox’s Crossroads Sports Complex Opens to Rave Reviews, On Time and Under Budget
New Lenox Waives Over $13,000 in Permit Fees for Park District, Church Projects
New Lenox Approves Site Plan for MBPRO Truck Repair on Moni Drive
Meeting Summary: New Lenox Board of Trustees for July 14, 2025
Manhattan Township, Road District Approve Budgets Totaling Over $3.1 Million
Manhattan Police Report
Meeting Summary and Briefs: Manhattan Fire Protection District Board of Trustees for June 16, 2025
Fire District Eyes Partnership with Villages for Enhanced Safety Inspections
Manhattan Fire District Plans Major Staff Expansion, Promotions in Early 2026
Manhattan Secures Irish Fest for Four More Years with Financial Support
Crete Township Wins Approval for New Digital Sign at Community Center