Land Use Committee: Monee Solar Projects Granted Extensions; Battery Storage Plans Dropped

Spread the love

Will County Land Use & Development Committee Meeting | December 2025

Article Summary: The Will County Land Use and Development Committee granted time extensions for two separate solar farm projects in Monee Township. During the review, it was revealed that the developer has removed the battery energy storage systems (BESS) from both applications, and Board Member Judy Ogalla clarified her stance on the projects based on their proximity to residential areas.

Monee Solar Extensions Key Points:

  • Project 1 (Monee Solar): Located at 26845 S. Will Center Road; extension approved 5-1.

  • Project 2 (Monee Solar West): Located at West Pauling Road and South Will Center Road; extension approved 6-0.

  • Major Change: The developer is no longer pursuing Battery Energy Storage Systems (BESS) at either location; the permits for those specific components will lapse.

  • New Deadline: Special use permits for the solar arrays are now valid through July 17, 2026.

The Will County Land Use and Development Committee on Thursday, Dec. 4, 2025, approved “first extensions” for two separate commercial solar energy facilities in Monee Township, giving the developers until July 2026 to obtain building permits.

The first project, Monee Solar, LLC, located at 26845 S. Will Center Road, was originally approved in January 2024. Staff reported that while the original approval included a special use permit for a Battery Energy Storage System (BESS), the applicant has decided not to move forward with the battery component. The extension request applies only to the solar farm itself.

Board Member Judy Ogalla voted against the extension for this specific site.

“I would not have supported this,” Ogalla said, referring to the original vote in early 2024. “That is way too close to residential… I would be a no on that.”

The committee voted 5-1 to approve the extension, with Ogalla voting no.

The second project, Monee Solar West, LLC, located at the northwest corner of West Pauling Road and South Will Center Road, also received an extension. Similar to the first project, the developer has dropped plans for a battery storage system at this site.

Ogalla voted in favor of this second extension, distinguishing it from the first project based on its location.

“The second one is not near residential, so I would be supporting that,” Ogalla noted.

The committee voted 6-0 to approve the extension for Monee Solar West. Both special use permits are now valid through July 17, 2026.

Leave a Comment





Latest News Stories

MH VB 7.15.25

Manhattan Approves 14 New Homes, Bike Path Completion in Whitefeather Subdivision

The Whitefeather subdivision is set for further expansion after the Manhattan Village Board approved the final plat for a new 14-home unit on Tuesday. The approval allows developer McDonnell Development...
WCO-PZ-July-15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...
Meeting Briefs

Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025

Frankfort Shed Relocation Approved: A homeowner on West Harvest Drive in Frankfort Township received a variance to reduce an east side-yard setback from 10 to 4 feet. The variance, sought by...
Meeting Briefs

Meeting Briefs: Manhattan Village Board for July 15, 2025

New Planning Commissioner Appointed: Mayor Mike Adrieansen appointed Gwen Petrella to the Manhattan Planning and Zoning Commission. The Village Board unanimously authorized the appointment for a term ending May 1, 2026....
manhattan fire district graphic logo.1

Manhattan Fire District Re-evaluating New Station Plans After Bids Come in Over Budget

Article Summary: Construction bids for a new Manhattan Fire Protection District station have come in over the district's maximum price, forcing officials to re-evaluate the project's scope. Chief Steve Malone...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property

An experiential culinary studio named Whisk & Flame is set to open in downtown Frankfort after the Village Board approved a series of special use permits and a significant parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Establishes New Zoning Rules to Attract Data Centers

The Village of Frankfort has amended its zoning ordinance to create a specific use category for data centers, a move designed to regulate and attract high-tech development. The Village Board...
Frankfort-Village-Board-Meeting-Graphic

Currie Motors Expansion Gets Approval with Site Modifications

Currie Motors on Lincoln Highway received approval from the Frankfort Village Board on Monday for a major change to its site plan, allowing for the construction of seven new parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $134,531 Maintenance Contract for Wastewater Plant Filters

The Frankfort Village Board has approved a $134,531.17 agreement with Veolia Water Technologies, Inc. for critical preventative maintenance at the Regional Wastewater Treatment Plant. The contract is for the complete...
Frankfort-Village-Board-Meeting-Graphic

Meeting Briefs: Frankfort Village Board for July 14, 2025

'Whisk & Flame' Culinary Studio Approved: The board approved "Whisk & Flame," an experiential culinary studio, for 10-12 Elwood Street. The project includes four special use permits for entertainment, liquor sales,...
WCO-Exec-Cmte-July-10.1

County Approves School Resource Officer, Multi-Year Planning Requirements

Will County approved hiring an additional sheriff's deputy for a school resource officer position that will be fully funded by Summit Hill School District 161, while also passing new transparency...
WCO-Exec-Cmte-July-10.2

County Addresses Senior Tax Exemption Processing Error

A processing error that cost County Board member Julie Berkowicz $600 in senior tax exemptions has prompted discussions about improving verification systems for property tax breaks. Will County Chief Assessment...
Meeting Briefs

Executive Committee Meeting July 10 Meeting Briefs

Liquor License Expansion: The county approved increasing Class C1 liquor licenses from eight to nine to accommodate Lockport Gas and Food LLC at 14747 W. 159th Street in Homer Glen....
frankfort-park-district

Meeting Briefs: Frankfort Park District Board for June 10, 2025

The Frankfort Park District Board of Commissioners discussed a legal dispute with the Five Oaks homeowners association over park development rules at its Tuesday meeting. Executive Director Gina Hassett reported...