Land Use Committee: Monee Solar Projects Granted Extensions; Battery Storage Plans Dropped
Will County Land Use & Development Committee Meeting | December 2025
Article Summary: The Will County Land Use and Development Committee granted time extensions for two separate solar farm projects in Monee Township. During the review, it was revealed that the developer has removed the battery energy storage systems (BESS) from both applications, and Board Member Judy Ogalla clarified her stance on the projects based on their proximity to residential areas.
Monee Solar Extensions Key Points:
-
Project 1 (Monee Solar): Located at 26845 S. Will Center Road; extension approved 5-1.
-
Project 2 (Monee Solar West): Located at West Pauling Road and South Will Center Road; extension approved 6-0.
-
Major Change: The developer is no longer pursuing Battery Energy Storage Systems (BESS) at either location; the permits for those specific components will lapse.
-
New Deadline: Special use permits for the solar arrays are now valid through July 17, 2026.
The Will County Land Use and Development Committee on Thursday, Dec. 4, 2025, approved “first extensions” for two separate commercial solar energy facilities in Monee Township, giving the developers until July 2026 to obtain building permits.
The first project, Monee Solar, LLC, located at 26845 S. Will Center Road, was originally approved in January 2024. Staff reported that while the original approval included a special use permit for a Battery Energy Storage System (BESS), the applicant has decided not to move forward with the battery component. The extension request applies only to the solar farm itself.
Board Member Judy Ogalla voted against the extension for this specific site.
“I would not have supported this,” Ogalla said, referring to the original vote in early 2024. “That is way too close to residential… I would be a no on that.”
The committee voted 5-1 to approve the extension, with Ogalla voting no.
The second project, Monee Solar West, LLC, located at the northwest corner of West Pauling Road and South Will Center Road, also received an extension. Similar to the first project, the developer has dropped plans for a battery storage system at this site.
Ogalla voted in favor of this second extension, distinguishing it from the first project based on its location.
“The second one is not near residential, so I would be supporting that,” Ogalla noted.
The committee voted 6-0 to approve the extension for Monee Solar West. Both special use permits are now valid through July 17, 2026.
Latest News Stories
Illini Final Four trip expected to benefit University of Illinois, state of Indiana
Trump makes history at Supreme Court amid landmark birthright citizenship challenge
New Hampshire school district sued over transgender policies
Trump watches as high court hears challenge to his birthright citizenship order
Illinois Quick Hits: Prtizker says Trump order is unconstitutional
U of I pressed on costly abandoned development project, stance on DEI directives
Trump says Iran’s new leader wants ceasefire
‘Conversion therapy’ bans in IL, other states, in danger, after SCOTUS ruling
Lincoln-Way 210 Approves Student Registration and Meal Fee Increases for 2026-2027
County Board Approves Peotone Solar Farm Amid Debates Over Union Labor and Tornado Safety
Lincoln-Way West Offense Explodes in 12-2 Victory Over Revere
Illinois business leaders press lawmakers as child care costs face scrutiny